9353 N WINNETKA AVE 91311
Certificate Information: 9353 N WINNETKA AVE 91311
- Application / Permit
- 20016-10000-16561
- Plan Check / Job No.
- B20LA12222
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INSTALLATION OF MODULAR LIFT VLM ANCHORAGE.
- Permit Issued
- Issued on 10/13/2020
- Issuing Office
- Current Status
- Issued on 10/13/2020
Permit Application Status History
| Submitted | 7/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2020 | SHANGQIN XIE |
| Corrections Issued | 7/15/2020 | SHANGQIN XIE |
| Applicant returned to address corrections | 9/15/2020 | CRISTINA SALAZAR |
| Building Plans Picked Up | 9/17/2020 | APPLICANT |
| Plan Check Approved | 10/9/2020 | FERNANDO FLORES |
| Issued | 10/13/2020 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Southwest Material Handling Inc; Lic. No.: 712327-D24 | P O BOX 1070 MIRA LOMA, CA 91752 |
| Engineer | Lee,, James Kwon; Lic. No.: S6493 | 1386 LA LOMA RD PASADENA, CA 91105 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/15/2020 | No Access for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 10/20/2020 | Partial Inspection | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 10/30/2020 | Conditional Approval | JEFFREY FULTON |
| Final | 11/5/2020 | Corrections Issued | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 11/5/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 11/5/2020 | Approved | JEFFREY FULTON |
| Final | 2/2/2021 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 2/2/2021 | SGSOV Not Ready | JEFFREY FULTON |
| Final | 2/17/2021 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 2/17/2021 | SGSOV Not Ready | JEFFREY FULTON |