3943 S WESTSIDE AVE 90008
Certificate Information: 3943 S WESTSIDE AVE 90008
- Application / Permit
- 20016-10000-16460
- Plan Check / Job No.
- B20LA12183
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/8/2022
- Issuing Office
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2020 | AMIR DANAI |
| Corrections Issued | 7/14/2020 | AMIR DANAI |
| Applicant returned to address corrections | 9/23/2021 | SINA KHOSRAVI |
| Plan Check Approved | 1/28/2022 | SINA KHOSRAVI |
| Building Plans Picked Up | 2/1/2022 | APPLICANT |
| Issued | 3/8/2022 | APPLICANT |
| CofO in Progress | 12/1/2023 | ANTHONY EGSON |
| CofO Issued | 12/14/2023 | DEROLD HAUFF |
| Permit Finaled | 12/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/28/2021 | JEANIE LAM |
| Sewer availability | Cleared | 6/28/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 1/5/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Greene,, Ronald Ray; Lic. No.: C33049 | 2418 TORRANCE BLVD TORRANCE, CA 90501 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/7/2022 | Partial Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/2/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/8/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/30/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 8/30/2022 | Approved | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 11/16/2022 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 11/30/2022 | Approved | ANTHONY EGSON |
| Insulation | 12/16/2022 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/12/2023 | Not Ready for Inspection | JULIAN AMAYA |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2023 | Corrections Issued | JULIAN AMAYA |
| BUILDING-Rough-Frame | 1/20/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/25/2023 | Partial Approval | ANTHONY EGSON |
| Insulation | 2/2/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 2/2/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 2/14/2023 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 4/25/2023 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 4/25/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 4/25/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/7/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 10/2/2023 | Approved | ANTHONY EGSON |
| Final | 10/2/2023 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 10/2/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 10/2/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 10/2/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/2/2023 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 10/2/2023 | Approved | ANTHONY EGSON |
| Final | 11/30/2023 | OK to Issue CofO | ANTHONY EGSON |