3943 S WESTSIDE AVE 90008

Certificate Information: 3943 S WESTSIDE AVE 90008

Application / Permit
20016-10000-16460
Plan Check / Job No.
B20LA12183
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/8/2022
Issuing Office
Current Status
CofO Issued on 12/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/14/2020 AMIR DANAI
Corrections Issued 7/14/2020 AMIR DANAI
Applicant returned to address corrections 9/23/2021 SINA KHOSRAVI
Plan Check Approved 1/28/2022 SINA KHOSRAVI
Building Plans Picked Up 2/1/2022 APPLICANT
Issued 3/8/2022 APPLICANT
CofO in Progress 12/1/2023 ANTHONY EGSON
CofO Issued 12/14/2023 DEROLD HAUFF
Permit Finaled 12/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/28/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/28/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 6/28/2021 JEANIE LAM
Sewer availability Cleared 6/28/2021 JEANIE LAM
Construction near power lines Cleared 1/5/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Greene,, Ronald Ray; Lic. No.: C33049 2418 TORRANCE BLVD      TORRANCE, CA 90501

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/7/2022 Partial Inspection ANTHONY EGSON
Footing/Foundation/Slab 8/2/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 8/8/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 8/30/2022 Approved ANTHONY EGSON
Underground Mechanical 8/30/2022 Approved ANTHONY EGSON
Rough-Elec/Plmb/HVAC 11/16/2022 Corrections Issued ANTHONY EGSON
Rough-Elec/Plmb/HVAC 11/30/2022 Approved ANTHONY EGSON
Insulation 12/16/2022 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 1/12/2023 Not Ready for Inspection JULIAN AMAYA
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Corrections Issued JULIAN AMAYA
BUILDING-Rough-Frame 1/20/2023 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/25/2023 Partial Approval ANTHONY EGSON
Insulation 2/2/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 2/2/2023 Approved ANTHONY EGSON
Drywall Nailing 2/14/2023 Approved ALEJANDRO DE ARTOLA
Sewer 4/25/2023 Approved ALIZAH MAYAGOITIA
Shower Pan 4/25/2023 Approved ALIZAH MAYAGOITIA
Underground Mechanical 4/25/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/7/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/2/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 10/2/2023 Approved ANTHONY EGSON
Final 10/2/2023 Corrections Issued ANTHONY EGSON
Gas Test 10/2/2023 Approved ANTHONY EGSON
HVAC-Final 10/2/2023 Approved ANTHONY EGSON
PLUMBING-Final 10/2/2023 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/2/2023 SGSOV Approved ANTHONY EGSON
Smoke Detectors 10/2/2023 Approved ANTHONY EGSON
Final 11/30/2023 OK to Issue CofO ANTHONY EGSON