1650 W 78TH ST 90047

Certificate Information: 1650 W 78TH ST 90047

Application / Permit
20016-10000-16428
Plan Check / Job No.
B20LA12152
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
-ePLAN Adus. Proposed RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1027 & RAD-31-1028. Proposed (17’-2.5” X 23'-0") detached accessory dwelling init per ordinance.
Permit Issued
Issued on 10/9/2020
Issuing Office
Current Status
CofO Issued on 9/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 MICHAEL LOPEZ
Corrections Issued 7/30/2020 MICHAEL LOPEZ
Quality Review Completed 8/14/2020 MINYE PAK
Applicant returned to address corrections 9/15/2020 MICHAEL LOPEZ
Plan Check Approved 10/6/2020 MICHAEL LOPEZ
Issued 10/9/2020 APPLICANT
CofO in Progress 8/24/2021 FREDDIE RIVERA
CofO Issued 9/2/2021 DEROLD HAUFF
Permit Finaled 9/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 8/6/2020 WALTER RAMIREZ
Construction within easement Cleared 8/6/2020 WALTER RAMIREZ
Address approval Cleared 8/18/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 8/18/2020 CECILIO NAVARRO
Sewer availability Cleared 8/21/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/26/2020 CECILIO NAVARRO

Contact Information

Architect Leavitt,, Derek Chase; Lic. No.: C31212 8757 WASHINGTON BLVD.      CULVER CITY, CA 90232
Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 8757 WASHINGTON BLVD      CULVER CITY, CA 90232
Engineer Sveiven,, Shane; Lic. No.: C89133 5900 CANTERBURY DR APT A206      CULVER CITY, CA 90230
Engineer Tompos,, Eric Joseph; Lic. No.: C70218 7690 W NOTTINGHAM DR      NAPPANEE, IN 46550

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/27/2020 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 11/6/2020 Not Ready for Inspection FREDDIE RIVERA
Pre-Inspection 11/6/2020 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/10/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Approved FREDDIE RIVERA
Wood Frame 12/4/2020 Approved FREDDIE RIVERA
Sewer 12/11/2020 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Approved FREDDIE RIVERA
Sewer 2/2/2021 Partial Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Not Ready FREDDIE RIVERA
BUILDING-Rough-Frame 4/6/2021 Approved FREDDIE RIVERA
ELECTRICAL-Final 4/6/2021 Approved FREDDIE RIVERA
Final 4/6/2021 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 4/6/2021 Approved FREDDIE RIVERA
Green Building Final 4/6/2021 Approved FREDDIE RIVERA
Green Building Rough 4/6/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/6/2021 SGSOV Approved FREDDIE RIVERA
Service/Power Release 4/6/2021 Approved FREDDIE RIVERA
Smoke Detectors 4/6/2021 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 4/6/2021 Approved FREDDIE RIVERA
Final 4/28/2021 Corrections Issued FREDDIE RIVERA
Final 5/10/2021 Corrections Issued DAVID FEILER
Final 5/26/2021 Corrections Issued FREDDIE RIVERA
Final 8/23/2021 OK to Issue CofO FREDDIE RIVERA