1879 W 95TH ST 90047

Certificate Information: 1879 W 95TH ST 90047

Application / Permit
20016-10000-16427
Plan Check / Job No.
B20LA12151
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* new detached ADU .Permit to Install a RADCO Approved Factory Built Housing Unit over a raised floor foundation.
Permit Issued
Issued on 10/2/2020
Issuing Office
Current Status
CofO Issued on 7/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 ARSALAN SHABESTARI
Corrections Issued 8/3/2020 ARSALAN SHABESTARI
Quality Review Completed 8/19/2020 MINYE PAK
Plan Check Approved 9/24/2020 ARSALAN SHABESTARI
Issued 10/2/2020 APPLICANT
CofO in Progress 6/30/2021 FREDDIE RIVERA
Permit Finaled 7/27/2021 DEROLD HAUFF
CofO Issued 7/27/2021 DEROLD HAUFF
Permit Finaled 7/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 8/6/2020 WALTER RAMIREZ
Construction within easement Cleared 8/6/2020 WALTER RAMIREZ
ZI Cleared 8/12/2020 JOE LUCKEY
Address approval Cleared 8/18/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 8/18/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/20/2020 CECILIO NAVARRO
Sewer availability Cleared 8/21/2020 CECILIO NAVARRO

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 8757 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/20/2020 Approved FREDDIE RIVERA
Footing/Foundation/Slab 11/20/2020 Approved FREDDIE RIVERA
METHANE-Barrier 11/20/2020 Approved FREDDIE RIVERA
METHANE-Subgrade 11/20/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Approved FREDDIE RIVERA
Sewer 2/24/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/17/2021 SGSOV Not Ready FREDDIE RIVERA
BUILDING-Rough-Frame 4/8/2021 Approved FREDDIE RIVERA
Final 4/8/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 4/8/2021 Approved FREDDIE RIVERA
Green Building Rough 4/8/2021 Approved FREDDIE RIVERA
METHANE-Final 4/8/2021 Approved FREDDIE RIVERA
METHANE-Rough 4/8/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/8/2021 SGSOV Approved FREDDIE RIVERA
Service/Power Release 4/8/2021 Approved FREDDIE RIVERA
Smoke Detectors 4/8/2021 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 4/8/2021 Approved FREDDIE RIVERA
Final 5/5/2021 Corrections Issued EUGENE CASSIDY
Final 5/18/2021 Corrections Issued DAVID FEILER
Final 6/3/2021 Not Ready for Inspection FREDDIE RIVERA
Final 6/30/2021 OK to Issue CofO FREDDIE RIVERA