5990 W AIRDROME ST 90035

Certificate Information: 5990 W AIRDROME ST 90035

Application / Permit
20016-10000-16426
Plan Check / Job No.
B20LA12149
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU .RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1027 & RAD-31-1028.
Permit Issued
Issued on 9/24/2020
Issuing Office
Current Status
CofO Issued on 7/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 ARSALAN SHABESTARI
Corrections Issued 8/3/2020 ARSALAN SHABESTARI
Quality Review Completed 8/17/2020 MINYE PAK
Applicant returned to address corrections 9/3/2020 ARSALAN SHABESTARI
Plan Check Approved 9/22/2020 ARSALAN SHABESTARI
Issued 9/24/2020 APPLICANT
CofO in Progress 5/18/2021 STUART CHAPMAN
Permit Finaled 7/3/2021 DEROLD HAUFF
CofO Issued 7/3/2021 DEROLD HAUFF
Permit Finaled 7/3/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 8/6/2020 WALTER RAMIREZ
ZI Cleared 8/12/2020 JOE LUCKEY
Address approval Cleared 8/18/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 8/18/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/20/2020 CECILIO NAVARRO
Sewer availability Cleared 8/20/2020 CECILIO NAVARRO

Contact Information

Contractor Yamadz Construction Inc; Lic. No.: 1066382-B       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/13/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 10/26/2020 Not Ready for Inspection DAVID CHAN
Excavation/Setback/Form/Re-Bar 10/30/2020 Corrections Issued RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Corrections Issued DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2020 Partial Approval DAVID CHAN
Sewer 12/11/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 12/16/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Barrier 12/16/2020 Approved STUART CHAPMAN
METHANE-Subgrade 12/16/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 12/17/2020 No Access for Inspection DAVID CHAN
METHANE-Barrier 12/17/2020 No Access for Inspection DAVID CHAN
METHANE-Subgrade 12/17/2020 No Access for Inspection DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2020 Approved DAVID CHAN
Sewer 1/28/2021 Not Ready for Inspection OSVALDO PARAMO
Sewer 2/2/2021 Approved STUART CHAPMAN
Pre-Inspection 3/10/2021 Partial Inspection ROBERT VORHIS
BUILDING-Rough-Frame 4/6/2021 Conditional Approval DAVID FEILER
ELECTRICAL-Final 4/6/2021 Not Ready for Inspection DAVID FEILER
Final 4/6/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 4/6/2021 Approved DAVID FEILER
Green Building Final 4/6/2021 Not Ready for Inspection DAVID FEILER
Green Building Rough 4/6/2021 Not Ready for Inspection DAVID FEILER
METHANE-Barrier 4/6/2021 Approved DAVID FEILER
METHANE-Final 4/6/2021 Approved DAVID FEILER
METHANE-Rough 4/6/2021 Not Ready for Inspection DAVID FEILER
METHANE-Subgrade 4/6/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 4/6/2021 SGSOV Not Ready DAVID FEILER
Service/Power Release 4/6/2021 Not Ready for Inspection DAVID FEILER
Smoke Detectors 4/6/2021 Approved DAVID FEILER
Verify Sprinkler Sign Off 4/6/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 4/26/2021 Approved STUART CHAPMAN
Final 4/26/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Final 4/26/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 4/26/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Not Required STUART CHAPMAN
Service/Power Release 4/26/2021 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 4/26/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 5/17/2021 Approved STUART CHAPMAN
Final 5/17/2021 OK to Issue CofO STUART CHAPMAN
Green Building Final 5/17/2021 Approved STUART CHAPMAN
HVAC-Final 5/17/2021 Approved STUART CHAPMAN
PLUMBING-Final 5/17/2021 Approved STUART CHAPMAN
Service/Power Release 5/17/2021 Approved STUART CHAPMAN