1620 N EUDORA AVE 90744

Certificate Information: 1620 N EUDORA AVE 90744

Application / Permit
20016-10000-16386
Plan Check / Job No.
B20LA12125
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 12/7/2020
Issuing Office
Current Status
CofO Issued on 9/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 STANLEY RAAP
Corrections Issued 7/16/2020 STANLEY RAAP
Applicant returned to address corrections 8/11/2020 CRISTINA SALAZAR
Applicant returned to address corrections 9/2/2020 TSE MING HUANG
Applicant returned to address corrections 9/21/2020 CRISTINA SALAZAR
Plan Check Approved 11/18/2020 GEORGE ALVAREZ
Building Plans Picked Up 11/20/2020 APPLICANT
Issued 12/7/2020 APPLICANT
CofO in Progress 7/11/2021 JOHN KLARIN
Permit Finaled 9/3/2021 DEROLD HAUFF
CofO Issued 9/3/2021 DEROLD HAUFF
Permit Finaled 9/3/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/11/2020 YEGANEH SADEGHI
Eng Process Fee Ord 176,300 Cleared 9/11/2020 YEGANEH SADEGHI
Sewer availability Cleared 9/11/2020 YEGANEH SADEGHI
Hydrant and Access approval Cleared 11/10/2020 KURT CORRAL

Contact Information

Contractor Apex Custom Construction; Lic. No.: 1026313-B PO BOX 2571      DOWNEY, CA 90242

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/14/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 12/14/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 12/14/2020 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 12/18/2020 Approved JOHN KLARIN
Footing/Foundation/Slab 12/18/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/26/2021 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 1/26/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Partial Approval JOHN KLARIN
Green Building Rough 1/26/2021 Approved JOHN KLARIN
METHANE-Rough 1/26/2021 Approved JOHN KLARIN
PLUMBING-Rough 1/26/2021 Approved JOHN KLARIN
Insulation 2/1/2021 Approved EUGENE CASSIDY
Drywall Nailing 2/18/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 2/18/2021 Partial Approval JOHN KLARIN
Interior/Exterior Lathing 3/5/2021 Approved JOHN KLARIN
Sewer 3/5/2021 Corrections Issued JOHN KLARIN
Underground Mechanical 3/5/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/8/2021 Approved JOHN KLARIN
ELECTRICAL-Final 4/8/2021 Approved JOHN KLARIN
Final 4/8/2021 Corrections Issued JOHN KLARIN
Green Building Final 4/8/2021 Corrections Issued JOHN KLARIN
HVAC-Final 4/8/2021 Approved JOHN KLARIN
PLUMBING-Final 4/8/2021 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 4/8/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 4/8/2021 Approved JOHN KLARIN
Final 5/5/2021 Corrections Issued JOHN KLARIN
Green Building Final 5/5/2021 Corrections Issued JOHN KLARIN
Final 7/6/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 7/6/2021 Approved EUGENE CASSIDY
Final 7/9/2021 OK to Issue CofO JOHN KLARIN