201 1/2 N VAN NESS AVE 90004

Certificate Information: 201 1/2 N VAN NESS AVE 90004

Application / Permit
20016-10000-16303
Plan Check / Job No.
B20LA12068
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF AN EXISTING DETACHED GARAGE INTO AN ADU PER GCS 65852.2 (E) (1) (A). 2 OF 2
Permit Issued
Issued on 1/26/2021
Issuing Office
Current Status
CofO Issued on 12/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 CRYSTEL MAALOUF
Corrections Issued 8/19/2020 CRYSTEL MAALOUF
Quality Review Completed 9/30/2020 WING SUEN
Building Plans Picked Up 10/7/2020 APPLICANT
Applicant returned to address corrections 1/5/2021 CRYSTEL MAALOUF
Plan Check Approved 1/15/2021 CRYSTEL MAALOUF
Issued 1/26/2021 APPLICANT
CofO in Progress 9/21/2022 JEFFREY MEAD
Permit Finaled 12/27/2022 DEROLD HAUFF
CofO Issued 12/27/2022 DEROLD HAUFF
Permit Finaled 12/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/4/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/4/2020 JEANIE LAM
Sewer availability Cleared 11/4/2020 JEANIE LAM
HPOZ Cleared 12/17/2020 CHRISTINA PARK

Contact Information

Contractor E N S Builders Inc; Lic. No.: 1022358-B 1212 WESTCHESTER PLACE      LOS ANGELES, CA 90019
Engineer Soliman,, John; Lic. No.: C80833 13785 PELICAN DR      RANCHO CUCAMONGA, CA 91739

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/26/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/15/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 5/10/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/2/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 7/2/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 7/2/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/8/2021 Conditional Approval CHRIS CHRISTENSEN
Green Building Rough 7/8/2021 Approved CHRIS CHRISTENSEN
Insulation 7/23/2021 Approved CHRIS CHRISTENSEN
Shower Pan 7/23/2021 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 8/10/2021 Conditional Approval CALEB MEISTER
BUILDING-Rough-Frame 8/13/2021 Approved JOSEPH MCGARRY
Drywall Nailing 8/13/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/13/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Final 12/10/2021 Corrections Issued STUART CHAPMAN
Final 12/10/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Final 12/10/2021 Approved STUART CHAPMAN
HVAC-Final 12/10/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Final 12/10/2021 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 12/10/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 12/10/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 12/17/2021 Approved CHRIS CHRISTENSEN
Final 12/17/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 12/17/2021 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Final 12/17/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 12/23/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 12/23/2021 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Final 12/23/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 12/28/2021 Approved JOSEPH MCGARRY
Final 12/28/2021 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Final 12/28/2021 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Final 12/28/2021 Approved JOSEPH MCGARRY
Final 9/20/2022 Partial Approval JEFFREY MEAD
Final 9/21/2022 OK to Issue CofO JEFFREY MEAD
HVAC-Final 9/21/2022 Approved JEFFREY MEAD