5707-5709 N KLUMP AVE 91601

Certificate Information: 5707-5709 N KLUMP AVE 91601

Application / Permit
20016-10000-16300
Plan Check / Job No.
B20LA12063
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX. 2 CAR CARPORT INTO AN ATTACHED ADU PER GCS 65852.2 (E) (1) (C) IN (E) DUPLEX STRUCTURE @ REAR OF LOT.
Permit Issued
Issued on 6/29/2021
Issuing Office
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 LUKE GONZALES
Corrections Issued 7/13/2020 LUKE GONZALES
Building Plans Picked Up 7/15/2020 APPLICANT
Applicant returned to address corrections 4/3/2021 AUNG SOE
Applicant returned to address corrections 4/4/2021 AUNG SOE
Applicant returned to address corrections 5/7/2021 LUKE GONZALES
Plan Check Approved 5/11/2021 LUKE GONZALES
Issued 6/29/2021 APPLICANT
CofO in Progress 7/27/2022 JOHN HAYES
Permit Finaled 8/25/2022 DANIEL ORRANTE
CofO Issued 8/25/2022 DANIEL ORRANTE
Permit Finaled 8/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/31/2020 GUILLERMO PETRA
Highway dedication Cleared 8/31/2020 GUILLERMO PETRA
Sewer availability Cleared 8/31/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 9/2/2020 GUILLERMO PETRA
Historic Resource Verification Cleared 10/20/2020 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 12/23/2020 DAVID URITA
ZI Cleared 12/23/2020 DAVID URITA

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/14/2022 Partial Approval JACK KARGODORIAN
Pre-Inspection 4/6/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 4/28/2022 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 4/28/2022 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 5/3/2022 Corrections Issued ARAM AVEDISIAN
Green Building Rough 5/10/2022 Approved ARAM AVEDISIAN
Wood Frame 5/10/2022 Approved ARAM AVEDISIAN
Insulation 5/16/2022 Approved CALEB MEISTER
Drywall Nailing 5/25/2022 Not Ready for Inspection CALEB MEISTER
Interior/Exterior Lathing 5/25/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 5/31/2022 Approved CALEB MEISTER
Drywall Nailing 7/18/2022 Approved DAVID MATSON
Final 7/18/2022 Corrections Issued DAVID MATSON
Green Building Final 7/18/2022 Not Ready for Inspection DAVID MATSON
SGSOV-Seismic Gas S/O Valve 7/18/2022 SGSOV Not Ready DAVID MATSON
Smoke Detectors 7/18/2022 Corrections Issued DAVID MATSON
Final 7/27/2022 OK to Issue CofO JOHN HAYES
Green Building Final 7/27/2022 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Approved JOHN HAYES
Smoke Detectors 7/27/2022 Approved JOHN HAYES