8501 N FALLBROOK AVE 3RD-FL 91304
Certificate Information: 8501 N FALLBROOK AVE 3RD-FL 91304
- Application / Permit
- 20016-10000-16298
- Plan Check / Job No.
- B20LA12060
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- T.I. 3RD FLOOR CORRIDOR 3256 S.F.
- Permit Issued
- Issued on 9/25/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 1/20/2021
Permit Application Status History
| Submitted | 7/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | TSE MING HUANG |
| Corrections Issued | 7/16/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 8/10/2020 | ZAW HAN |
| Plan Check Approved | 8/12/2020 | ZAW HAN |
| Building Plans Picked Up | 8/12/2020 | APPLICANT |
| Issued | 9/25/2020 | APPLICANT |
| Permit Finaled | 1/20/2021 | JEFFREY FULTON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Wilder,, Arthur J; Lic. No.: C27915 | 3859 CARDIFF AVENUE CULVER CITY, CA 90232 |
| Contractor | Pinnacle Contracting Corporation; Lic. No.: 665647-B | 21800 BURBANK BLVD #210 WOODLAND HILLS, CA 91367 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 10/26/2020 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 10/26/2020 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 11/5/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 11/13/2020 | No Access for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 11/16/2020 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 11/20/2020 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 11/30/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 12/1/2020 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 12/2/2020 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 12/4/2020 | Corrections Issued | JEFFREY FULTON |
| Final | 1/15/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 1/15/2021 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 1/15/2021 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 1/15/2021 | Approved | JEFFREY FULTON |
| Final | 1/20/2021 | Permit Finaled | JEFFREY FULTON |