5740 N COLDWATER CANYON AVE 91607

Certificate Information: 5740 N COLDWATER CANYON AVE 91607

Application / Permit
20016-10000-16265
Plan Check / Job No.
B20LA12034
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU Conversions. Convert existing detached garage into an ADU
Permit Issued
Issued on 3/31/2021
Issuing Office
Current Status
CofO Issued on 5/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 ARSALAN SHABESTARI
Corrections Issued 7/30/2020 ARSALAN SHABESTARI
Quality Review Completed 8/7/2020 PRANITA SHAH
Applicant returned to address corrections 12/14/2020 ARSALAN SHABESTARI
Plan Check Approved 2/5/2021 ARSALAN SHABESTARI
Issued 3/31/2021 APPLICANT
CofO in Progress 4/22/2022 CHRISTOPHE COCHRAN
CofO Issued 5/16/2022 RONALD MYRICK
Permit Finaled 5/16/2022 RONALD MYRICK

Permit Application Clearance Information

Construction near power lines Cleared 10/14/2020 RIDWAN HARDY
Construction within easement Cleared 10/14/2020 RIDWAN HARDY
Address approval Cleared 11/23/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/23/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/23/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Dh Remodel Services; Lic. No.: 1030925-B 5850 W 3RD STREET #160      LOS ANGELES, CA 90036

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2021 Approved RICHARD DOCKUS
Footing/Foundation/Slab 5/12/2021 Corrections Issued RICHARD DOCKUS
Underground Mechanical 5/24/2021 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 6/3/2021 Conditional Approval RICHARD DOCKUS
ELECTRICAL-Rough 6/10/2021 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 6/10/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 6/10/2021 Partial Approval RICHARD DOCKUS
Sewer 6/10/2021 Approved RICHARD DOCKUS
HVAC-Rough 6/18/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 6/28/2021 Approved RICHARD DOCKUS
HVAC-Rough 6/29/2021 Not Ready for Inspection RICHARD DOCKUS
Drywall Nailing 7/2/2021 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 7/7/2021 Approved RICHARD DOCKUS
Wood Frame 7/7/2021 Partial Approval RICHARD DOCKUS
Insulation 7/12/2021 Partial Approval DEANDRE HOFFMAN
Interior/Exterior Lathing 7/12/2021 Not Ready for Inspection DEANDRE HOFFMAN
Drywall Nailing 7/14/2021 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 No Access for Inspection ALAN MORELOS
Drywall Nailing 7/23/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/23/2021 Approved JAVIER RAMOS JR
Shower Pan 8/12/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 9/7/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 9/7/2021 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Final 9/7/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 9/8/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 9/8/2021 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Final 9/8/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Gas Test 9/29/2021 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/5/2022 Approved CHRISTOPHE COCHRAN
Final 1/5/2022 Corrections Issued CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 1/5/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 1/5/2022 Approved CHRISTOPHE COCHRAN
Final 2/17/2022 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Final 4/4/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 4/4/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 4/4/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Final 4/4/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 4/22/2022 OK to Issue CofO CHRISTOPHE COCHRAN