9957 N EL DORADO AVE 91331
Certificate Information: 9957 N EL DORADO AVE 91331
- Application / Permit
- 20016-10000-16261
- Plan Check / Job No.
- B20LA12030
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU conversions. EXISTING GARAGE CONVERSION TO accessory dwelling unit per LAMC 12.22 A.33(b)(5)
- Permit Issued
- Issued on 7/9/2021
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | MONICA RAMIREZ |
| Corrections Issued | 8/11/2020 | MONICA RAMIREZ |
| Quality Review Completed | 8/12/2020 | TU HUA |
| Applicant returned to address corrections | 4/5/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 4/12/2021 | MONICA RAMIREZ |
| Plan Check Approved | 7/9/2021 | MONICA RAMIREZ |
| Issued | 7/9/2021 | APPLICANT |
| CofO in Progress | 4/10/2023 | MICHEL ABAJAN |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/6/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | O'Brien,, Kathleen Anne; Lic. No.: C49498 | 1058 PACIFIC AVE SIMI VALLEY, CA 93065 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/1/2021 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 9/7/2021 | Approved | MICHAEL PELHAM |
| Underground Mechanical | 11/18/2021 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 11/23/2021 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 11/23/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/2/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 2/2/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| HVAC-Rough | 2/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 2/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 4/12/2022 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Rough | 4/12/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/12/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/14/2022 | Approved | MICHEL ABAJAN |
| Insulation | 7/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 10/4/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/4/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/7/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/5/2023 | Approved | MICHEL ABAJAN |
| Final | 4/5/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/5/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/5/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/5/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 4/5/2023 | Approved | MICHEL ABAJAN |
| Final | 4/10/2023 | OK to Issue CofO | MICHEL ABAJAN |