654 1/2 S SOTO ST 90023
Certificate Information: 654 1/2 S SOTO ST 90023
- Application / Permit
- 20016-10000-16168
- Plan Check / Job No.
- B20LA11976
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU PER LAMC A.33(c) AND (d)
- Permit Issued
- Issued on 1/18/2021
- Issuing Office
- Current Status
- CofO Issued on 1/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2020 | TSE MING HUANG |
| Corrections Issued | 7/22/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 11/16/2020 | AMIR DANAI |
| Plan Check Approved | 12/30/2020 | LUKE GONZALES |
| Issued | 1/18/2021 | APPLICANT |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| CofO in Progress | 12/21/2021 | RUBEN SALAS |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
| CofO Issued | 1/8/2022 | DEROLD HAUFF |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/17/2020 | JOE LUCKEY |
| Clean Up Green Up | Cleared | 8/17/2020 | JOE LUCKEY |
| ZA Case | Cleared | 8/17/2020 | JOE LUCKEY |
| Address approval | Cleared | 8/26/2020 | JEANIE LAM |
| Sewer availability | Cleared | 8/26/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 11/23/2020 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 12/30/2020 | LUKE GONZALES |
Contact Information
| Contractor | Inspyre Home Construction Llc; Lic. No.: 1058662-B | 22 S SUNNYSLOPE AVE PASADENA, CA 91107 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/9/2021 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 2/22/2021 | Corrections Issued | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Conditional Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 3/2/2021 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Partial Approval | ROBERT VORHIS |
| METHANE-Rough | 4/14/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Insulation | 5/13/2021 | Partial Approval | ROBERT VORHIS |
| Interior/Exterior Lathing | 5/13/2021 | Corrections Issued | ROBERT VORHIS |
| Insulation | 6/2/2021 | Approved | ROBERT VORHIS |
| METHANE-Rough | 6/2/2021 | Approved | ROBERT VORHIS |
| Wood Frame | 6/2/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 6/7/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 6/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 8/26/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 8/26/2021 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 8/26/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 9/9/2021 | Partial Inspection | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 9/9/2021 | SGSOV Approved | ROBERT VORHIS |
| Smoke Detectors | 9/9/2021 | Approved | ROBERT VORHIS |
| Final | 11/29/2021 | Partial Inspection | RUBEN SALAS |
| Final | 12/20/2021 | OK to Issue CofO | RUBEN SALAS |