1390 N AVENIDA DE CORTEZ 90272
Certificate Information: 1390 N AVENIDA DE CORTEZ 90272
- Application / Permit
- 20016-10000-16068
- Plan Check / Job No.
- B20LA11916
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- RENOVATION AND ALTERATION OF EXISTING 1 STORY SFD W/ATTACHED GARAGE. NO CHANGE TO (E) HOME FOOTPRINT OR ROOF LINE
- Permit Issued
- Issued on 10/12/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/4/2024
Permit Application Status History
| Submitted | 7/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | ZAW HAN |
| Corrections Issued | 7/13/2020 | ZAW HAN |
| Applicant returned to address corrections | 8/6/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 9/17/2020 | ZAW HAN |
| Issued | 10/12/2020 | APPLICANT |
| Building Plans Picked Up | 11/12/2020 | APPLICANT |
| Permit Finaled | 3/4/2024 | EVAN COOPER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/20/2020 | PATRICK MISCHLICH |
| Coastal Zone | Cleared | 8/20/2020 | KENTON TRINH |
| ZI | Cleared | 8/20/2020 | KENTON TRINH |
Contact Information
| Architect | Stanton,, Quentin David; Lic. No.: C35887 | 1751 COLORADO BLVD #333 LOS ANGELES, CA 90041 |
| Contractor | Triple A Construction; Lic. No.: 1058766-B | 2014 ROUNDS ST DELANO, CA 93215 |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 600 WILSHIRE BLVD 760 LOS ANGELES, CA 90017 |
Inspector Information
| MICHAEL ALLEN, (310) 914-3886 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/25/2020 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 12/10/2020 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 12/10/2020 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 1/15/2021 | Partial Inspection | ANDREW NAVE |
| Wood Frame | 1/26/2021 | No Access for Inspection | ANDREW NAVE |
| Wood Frame | 2/3/2021 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Rough | 3/2/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 3/5/2021 | Not Ready for Inspection | ANDREW NAVE |
| Interior/Exterior Lathing | 3/9/2021 | Partial Approval | ANDREW NAVE |
| Deputy Drilled-In Anchors | 4/14/2021 | Approved | ROBERT SHELLY |
| Excavation/Setback/Form/Re-Bar | 4/27/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 11/4/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 11/4/2021 | Approved | ANDREW NAVE |
| HVAC-Rough | 11/4/2021 | Approved | ANDREW NAVE |
| Special/Order Compliance | 11/4/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 11/10/2021 | Approved | ANDREW NAVE |
| Insulation | 11/10/2021 | Approved | ANDREW NAVE |
| Drywall Nailing | 11/17/2021 | Approved | ANDREW NAVE |
| Shower Pan | 11/22/2021 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Shower Pan | 11/23/2021 | Corrections Issued | ANDREW NAVE |
| Interior/Exterior Lathing | 12/1/2021 | Approved | ANDREW NAVE |
| Shower Pan | 12/1/2021 | Approved | ANDREW NAVE |
| HVAC-Final | 11/9/2022 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 11/9/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 11/10/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 11/10/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 11/14/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Final | 11/14/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 11/17/2022 | Conditional Approval | BRENDAN LOONEY |
| Final | 11/18/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 11/18/2022 | Approved | BRENDAN LOONEY |
| Final | 1/11/2024 | Not Ready for Inspection | EVAN COOPER |
| Final | 3/4/2024 | Permit Finaled | EVAN COOPER |