4613 W 29TH ST 90016
Certificate Information: 4613 W 29TH ST 90016
- Application / Permit
- 20016-10000-16007
- Plan Check / Job No.
- B20LA11869
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Check CONVERT EXISTING 10X18 GARAGE INTO ADU
- Permit Issued
- Issued on 2/3/2021
- Issuing Office
- Current Status
- CofO Issued on 7/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | JOE VO |
| Corrections Issued | 7/28/2020 | JOE VO |
| Quality Review Completed | 8/3/2020 | MINYE PAK |
| Plan Check Approved | 1/26/2021 | JOE VO |
| Issued | 2/3/2021 | APPLICANT |
| CofO in Progress | 7/6/2021 | STUART CHAPMAN |
| Permit Finaled | 7/10/2021 | DEROLD HAUFF |
| CofO Issued | 7/10/2021 | DEROLD HAUFF |
| Permit Finaled | 7/10/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2020 | ELAINE LEI |
| Sewer availability | Cleared | 8/27/2020 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/5/2021 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/24/2021 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/24/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 3/24/2021 | Partial Approval | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 4/5/2021 | No Result Entered | CHARLENE BUSTAMANTE |
| BUILDING-Rough-Frame | 4/12/2021 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Final | 4/12/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/12/2021 | Approved | STUART CHAPMAN |
| Insulation | 4/20/2021 | Partial Inspection | MORRIS JACKSON |
| Pre-Inspection | 4/20/2021 | Partial Inspection | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 5/5/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/5/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Shower Pan | 5/13/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/27/2021 | Approved | STUART CHAPMAN |
| Final | 5/27/2021 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2021 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 5/27/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 6/7/2021 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/7/2021 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 6/7/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 6/11/2021 | Approved | STUART CHAPMAN |
| Final | 6/11/2021 | Partial Approval | STUART CHAPMAN |
| HVAC-Final | 6/11/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 6/11/2021 | Approved | STUART CHAPMAN |