2752 N KNOX AVE 90039

Certificate Information: 2752 N KNOX AVE 90039

Application / Permit
20016-10000-15980
Plan Check / Job No.
B20LA11844
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* SUPPLEMENTAL TO PERMIT 17010-10000-03438 TO REVISE SCOPE OF WORK FROM "(N) 2 STORY ACCESSORY DWELLING UNIT" TO "CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT & PATIO COVER ADDITION"
Permit Issued
Issued on 12/3/2020
Issuing Office
Current Status
Permit Finaled on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 LAMAR DAVIS
Corrections Issued 7/30/2020 LAMAR DAVIS
Quality Review Completed 8/7/2020 TU HUA
Applicant returned to address corrections 10/5/2020 LAMAR DAVIS
Applicant returned to address corrections 10/21/2020 LAMAR DAVIS
Applicant returned to address corrections 10/27/2020 LAMAR DAVIS
Applicant returned to address corrections 10/29/2020 LAMAR DAVIS
Plan Check Approved 11/20/2020 LAMAR DAVIS
Issued 12/3/2020 APPLICANT
CofO in Progress 8/22/2022 THOMAS LOGRASSO
No Progress 8/26/2022 THOMAS LOGRASSO
Permit Finaled 8/30/2022 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/2/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 9/2/2020 RENZ SORIANO
Sewer availability Cleared 9/2/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/10/2020 RENZ SORIANO
ZI Cleared 9/30/2020 SARAHI ORTEGA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/22/2021 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 1/22/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 1/28/2021 Corrections Issued COREY HUPP
Footing/Foundation/Slab 2/5/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/20/2021 Partial Approval CRAIG VAUGHAN
Green Building Rough 5/20/2021 Not Ready for Inspection CRAIG VAUGHAN
MERV13>=Rough 5/20/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 5/27/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 5/27/2021 Approved HAMIK HARTOUNIAN
Wood Frame 5/27/2021 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/11/2021 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 6/11/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 6/11/2021 Approved HAMIK HARTOUNIAN
MERV13>=Rough 6/11/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/7/2021 Approved SCOTT FINNILA
ELECTRICAL-Rough 7/7/2021 Approved SCOTT FINNILA
Insulation 7/7/2021 Approved SCOTT FINNILA
Drywall Nailing 8/4/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 8/4/2021 Approved THOMAS LOGRASSO
Shower Pan 8/4/2021 Approved THOMAS LOGRASSO
Final 5/25/2022 Corrections Issued THOMAS LOGRASSO
Green Building Final 5/25/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 5/25/2022 Approved THOMAS LOGRASSO
Final 6/30/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 6/30/2022 Not Ready for Inspection THOMAS LOGRASSO
Final 8/19/2022 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 8/19/2022 Approved THOMAS LOGRASSO