320 1/2 W 91ST PL 90003

Certificate Information: 320 1/2 W 91ST PL 90003

Application / Permit
20016-10000-15946
Plan Check / Job No.
B20LA11819
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED [18X18] GARAGE INTO ONE BEDROOM ADU
Permit Issued
Issued on 12/29/2020
Issuing Office
Current Status
CofO Issued on 1/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 FERNANDO FLORES
Corrections Issued 7/23/2020 FERNANDO FLORES
Plan Check Approved 11/4/2020 JESSE JIMENEZ
Issued 12/29/2020 APPLICANT
Building Plans Picked Up 1/7/2021 APPLICANT
CofO in Progress 1/3/2023 LILIANA PORTILLO
CofO Issued 1/4/2023 DEROLD HAUFF
Permit Finaled 1/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/2/2020 THOMAS LANG
Sewer availability Cleared 9/2/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/4/2020 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 5/3/2021 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/17/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 5/24/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 6/2/2021 Corrections Issued EUGENE CASSIDY
Sewer 6/2/2021 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 2/28/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 2/28/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/16/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/18/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 5/18/2022 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 6/3/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 6/3/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 6/15/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 7/14/2022 Approved LILIANA PORTILLO
Gas Test 7/14/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 7/14/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/16/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 8/16/2022 Corrections Issued LILIANA PORTILLO
Underground Mechanical 8/16/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 9/13/2022 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Approved LILIANA PORTILLO
HVAC-Rough 9/13/2022 Approved LILIANA PORTILLO
Insulation 9/13/2022 Approved LILIANA PORTILLO
MERV13>=Rough 9/13/2022 Approved LILIANA PORTILLO
Drywall Nailing 9/29/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 9/29/2022 Partial Approval LILIANA PORTILLO
Drywall Nailing 10/20/2022 Approved LILIANA PORTILLO
Footing/Foundation/Slab 10/20/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/20/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 11/3/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/3/2022 Corrections Issued LILIANA PORTILLO
Final 11/3/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 11/3/2022 Corrections Issued LILIANA PORTILLO
Green Building Rough 11/3/2022 Approved LILIANA PORTILLO
HVAC-Final 11/3/2022 Approved LILIANA PORTILLO
MERV13>=Final 11/3/2022 Approved LILIANA PORTILLO
PLUMBING-Final 11/3/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 11/3/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/20/2022 Approved LILIANA PORTILLO
Final 12/20/2022 Conditional Approval LILIANA PORTILLO
Green Building Final 12/20/2022 Approved LILIANA PORTILLO
HVAC-Final 12/20/2022 Approved LILIANA PORTILLO
PLUMBING-Final 12/20/2022 Approved LILIANA PORTILLO
Service/Power Release 12/20/2022 Approved LILIANA PORTILLO