5105 N WOODMAN AVE 91423
Certificate Information: 5105 N WOODMAN AVE 91423
- Application / Permit
- 20016-10000-15900
- Plan Check / Job No.
- B20LA11786
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: USING (4) SPECIAL CANTILEVER COLUMN SYSTEM.
- Permit Issued
- Issued on 5/6/2021
- Issuing Office
- Current Status
- CofC Issued on 2/16/2022
Permit Application Status History
| Submitted | 7/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | VARAND SARKISIAN |
| Corrections Issued | 8/4/2020 | VARAND SARKISIAN |
| Quality Review Completed | 8/4/2020 | HANS SANTIAGO |
| Plan Check Approved | 12/4/2020 | VARAND SARKISIAN |
| Issued | 5/6/2021 | APPLICANT |
| OK for CofC | 1/25/2022 | KENNETH ROBERTS |
| CofC Issued | 2/16/2022 | KENNETH ROBERTS |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/5/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Global Builders Inc; Lic. No.: 1045058-B | 1740 E GARRY AVENUE SANTA ANA, CA 92705 |
| Engineer | Watson,, Darren S; Lic. No.: C87717 | 3704 MIDVALE AVE 6 LOS ANGELES, CA 90034 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 9/17/2021 | Corrections Issued | JOE VELASQUEZ |
| Deputy Steel/Welding | 9/21/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 10/4/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 10/4/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 10/5/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 10/5/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 10/6/2021 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 11/3/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 11/3/2021 | Corrections Issued | JOE VELASQUEZ |
| Wood Frame | 12/2/2021 | Approved | KENNETH ROBERTS |
| Interior/Exterior Lathing | 12/21/2021 | Corrections Issued | BRUCE CAMPBELL |
| Final | 1/25/2022 | OK for CofC | KENNETH ROBERTS |
| Interior/Exterior Lathing | 1/25/2022 | Approved | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Gas Company | KENNETH ROBERTS |
| Smoke Detectors | 1/25/2022 | Approved | KENNETH ROBERTS |