10208 S HOBART BLVD 90047
Certificate Information: 10208 S HOBART BLVD 90047
- Application / Permit
- 20016-10000-15811
- Plan Check / Job No.
- B20LA11755
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Adu. CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER ORDINANCE. SCOPE WILL ALSO INCLUDE A (17'-9" X 7'-0") ADDITION TO THE REAR. ***SEE COMMENTS***
- Permit Issued
- Issued on 11/30/2020
- Issuing Office
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | MICHAEL LOPEZ |
| Corrections Issued | 7/23/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 7/29/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 10/1/2020 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/27/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 10/29/2020 | MICHAEL LOPEZ |
| Issued | 11/30/2020 | APPLICANT |
| CofO in Progress | 11/16/2023 | ENRIQUE MIRELES |
| Permit Finaled | 11/21/2023 | DEROLD HAUFF |
| Permit Finaled | 11/21/2023 | DEROLD HAUFF |
| CofO Issued | 11/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/7/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 8/7/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2020 | PAMELA TENEZA |
| Sewer availability | Cleared | 8/17/2020 | PAMELA TENEZA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/7/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| METHANE-Barrier | 1/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 1/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 1/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/13/2021 | No Access for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/13/2021 | No Access for Inspection | FREDDIE RIVERA |
| METHANE-Barrier | 1/13/2021 | No Access for Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 1/13/2021 | No Access for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 1/13/2021 | No Access for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/20/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/20/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| METHANE-Barrier | 1/20/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 1/20/2021 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 1/20/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/15/2021 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 4/15/2021 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 4/15/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/7/2021 | Partial Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 7/7/2021 | Corrections Issued | ANSON MAGLASANG |
| Green Building Rough | 7/7/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| METHANE-Rough | 7/7/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 7/7/2021 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 8/4/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 8/4/2021 | Conditional Approval | FREDDIE RIVERA |
| Insulation | 8/4/2021 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 8/4/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/7/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/7/2021 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 9/7/2021 | Approved | FREDDIE RIVERA |
| Insulation | 10/6/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 10/14/2021 | No Access for Inspection | ADAM ESCOTO |
| Drywall Nailing | 11/4/2021 | Approved | FREDDIE RIVERA |
| Shower Pan | 12/8/2021 | Corrections Issued | FREDDIE RIVERA |
| Shower Pan | 12/13/2021 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/19/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 4/19/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Final | 5/23/2022 | Approved | HORACE FULTZ |
| Final | 12/6/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/6/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 12/6/2022 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/6/2022 | Approved | ENRIQUE MIRELES |
| Final | 12/28/2022 | Conditional Approval | ENRIQUE MIRELES |
| Final | 11/15/2023 | OK to Issue CofO | ENRIQUE MIRELES |