10437 N LAS LUNITAS AVE 91042
Certificate Information: 10437 N LAS LUNITAS AVE 91042
- Application / Permit
- 20016-10000-15647
- Plan Check / Job No.
- B20LA11597
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Check. Convert existing detached garage into an accessory dwelling unit per state la GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 9/29/2020
- Issuing Office
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | MICHAEL LOPEZ |
| Corrections Issued | 7/23/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 8/7/2020 | PRANITA SHAH |
| Plan Check Approved | 9/21/2020 | MICHAEL LOPEZ |
| Issued | 9/29/2020 | APPLICANT |
| CofO in Progress | 6/28/2022 | MATTHEW NELSON |
| Permit Finaled | 8/17/2022 | DANIEL ORRANTE |
| CofO Issued | 8/17/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/17/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/28/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/7/2021 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/7/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/26/2021 | Approved | MATTHEW NELSON |
| Special/Order Compliance | 2/2/2021 | Corrections Issued | DAVID MATSON |
| BUILDING-Rough-Frame | 3/8/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 3/8/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 3/8/2021 | Partial Approval | MATTHEW NELSON |
| Special/Order Compliance | 4/8/2021 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/19/2021 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 4/19/2021 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/21/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 5/21/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/10/2021 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/10/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 6/10/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/10/2021 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/21/2021 | Approved | MATTHEW NELSON |
| Wood Frame | 6/21/2021 | Approved | MATTHEW NELSON |
| Insulation | 9/16/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/16/2021 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 10/14/2021 | Approved | MATTHEW NELSON |
| Pre-Inspection | 2/9/2022 | Corrections Issued | MATTHEW NELSON |
| Final | 5/18/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 5/18/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 5/18/2022 | Approved | MATTHEW NELSON |
| Final | 6/21/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 6/21/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 6/27/2022 | Approved | MATTHEW NELSON |
| Final | 6/27/2022 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 6/27/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 6/27/2022 | Approved | MATTHEW NELSON |