10437 N LAS LUNITAS AVE 91042

Certificate Information: 10437 N LAS LUNITAS AVE 91042

Application / Permit
20016-10000-15647
Plan Check / Job No.
B20LA11597
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Check. Convert existing detached garage into an accessory dwelling unit per state la GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 9/29/2020
Issuing Office
Current Status
CofO Issued on 8/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 MICHAEL LOPEZ
Corrections Issued 7/23/2020 MICHAEL LOPEZ
Quality Review Completed 8/7/2020 PRANITA SHAH
Plan Check Approved 9/21/2020 MICHAEL LOPEZ
Issued 9/29/2020 APPLICANT
CofO in Progress 6/28/2022 MATTHEW NELSON
Permit Finaled 8/17/2022 DANIEL ORRANTE
CofO Issued 8/17/2022 DANIEL ORRANTE
Permit Finaled 8/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/28/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/28/2020 CECILIO NAVARRO
Sewer availability Cleared 8/28/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/7/2021 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 1/7/2021 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 1/26/2021 Approved MATTHEW NELSON
Special/Order Compliance 2/2/2021 Corrections Issued DAVID MATSON
BUILDING-Rough-Frame 3/8/2021 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 3/8/2021 Not Ready for Inspection MATTHEW NELSON
Rough-Elec/Plmb/HVAC 3/8/2021 Partial Approval MATTHEW NELSON
Special/Order Compliance 4/8/2021 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 4/19/2021 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 4/19/2021 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 5/21/2021 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 5/21/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 6/10/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 6/10/2021 Approved MATTHEW NELSON
Green Building Rough 6/10/2021 Approved MATTHEW NELSON
PLUMBING-Rough 6/10/2021 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 6/21/2021 Approved MATTHEW NELSON
Wood Frame 6/21/2021 Approved MATTHEW NELSON
Insulation 9/16/2021 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 9/16/2021 Approved JUSTIN HAWLEY
Drywall Nailing 10/14/2021 Approved MATTHEW NELSON
Pre-Inspection 2/9/2022 Corrections Issued MATTHEW NELSON
Final 5/18/2022 Corrections Issued MATTHEW NELSON
Green Building Final 5/18/2022 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 5/18/2022 SGSOV Approved MATTHEW NELSON
Smoke Detectors 5/18/2022 Approved MATTHEW NELSON
Final 6/21/2022 Corrections Issued MATTHEW NELSON
Green Building Final 6/21/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 6/27/2022 Approved MATTHEW NELSON
Final 6/27/2022 OK to Issue CofO MATTHEW NELSON
HVAC-Final 6/27/2022 Approved MATTHEW NELSON
PLUMBING-Final 6/27/2022 Approved MATTHEW NELSON