232-232 1/2 W 78TH ST 90003

Certificate Information: 232-232 1/2 W 78TH ST 90003

Application / Permit
20016-10000-15639
Plan Check / Job No.
B20LA11762
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY (2) ADUs AT REAR OF LOT.
Permit Issued
Issued on 10/22/2021
Issuing Office
Current Status
CofO Issued on 2/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 JOE VO
Corrections Issued 7/29/2020 JOE VO
Quality Review Completed 8/3/2020 MINYE PAK
Applicant returned to address corrections 8/18/2021 JOE VO
Applicant returned to address corrections 9/7/2021 JOE VO
Plan Check Approved 10/5/2021 JOE VO
Issued 10/22/2021 APPLICANT
CofO in Progress 1/27/2023 LILIANA PORTILLO
Permit Finaled 2/2/2023 DEROLD HAUFF
CofO Issued 2/2/2023 DEROLD HAUFF
Permit Finaled 2/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/15/2021 JEANIE LAM
Sewer availability Cleared 2/11/2021 PAMELA TENEZA
Eng Process Fee Ord 176,300 Cleared 5/27/2021 JEANIE LAM
Low Impact Development Cleared 7/7/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/27/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: NA65104       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2022 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 5/16/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/25/2022 Corrections Issued LILIANA PORTILLO
Deputy Reinf. Concrete 6/2/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/6/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 6/10/2022 Corrections Issued LILIANA PORTILLO
Special/Order Compliance 6/10/2022 Partial Inspection SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/22/2022 Partial Approval HORACE FULTZ
Deputy Drilled-In Anchors 7/25/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 8/1/2022 Approved LILIANA PORTILLO
Deputy Wood Construction 8/2/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 8/31/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Approved LILIANA PORTILLO
Sewer 8/31/2022 Approved LILIANA PORTILLO
Underground Mechanical 8/31/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 9/8/2022 Approved MICHAEL LEWIS
HVAC-Rough 9/8/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 9/8/2022 Approved MICHAEL LEWIS
Wood Frame 9/8/2022 Corrections Issued MICHAEL LEWIS
Insulation 9/19/2022 Corrections Issued LILIANA PORTILLO
Shower Pan 9/19/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 9/26/2022 Approved LILIANA PORTILLO
Shower Pan 9/26/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/6/2022 Approved LILIANA PORTILLO
Final 12/6/2022 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 12/6/2022 Approved LILIANA PORTILLO
Green Building Final 12/6/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 12/6/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 12/6/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 12/6/2022 Not Ready for Inspection LILIANA PORTILLO
Verify Sprinkler Sign Off 12/6/2022 Approved LILIANA PORTILLO
Final 1/11/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 1/11/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/11/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 1/11/2023 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 1/11/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 1/17/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/17/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 1/17/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/20/2023 Partial Inspection SCOTT FINNILA
Green Building Final 1/20/2023 Approved SCOTT FINNILA
Service/Power Release 1/20/2023 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 1/26/2023 Approved LILIANA PORTILLO
Final 1/26/2023 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 1/26/2023 Approved LILIANA PORTILLO
PLUMBING-Final 1/26/2023 Approved LILIANA PORTILLO
Service/Power Release 1/26/2023 Approved LILIANA PORTILLO