10919 W STRATHMORE DR 90024
Certificate Information: 10919 W STRATHMORE DR 90024
- Application / Permit
- 20016-10000-15550
- Plan Check / Job No.
- B20LA11555
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install New Wood Shear walls. Provide HSS Steel bracing for shear/drag transfer to new shear wall
- Permit Issued
- Issued on 6/16/2022
- Issuing Office
- Current Status
- CofC Issued on 12/12/2022
Permit Application Status History
| Submitted | 8/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | HANS SANTIAGO |
| Corrections Issued | 8/24/2020 | HANS SANTIAGO |
| Quality Review Completed | 8/25/2020 | SAI KHUM |
| Applicant returned to address corrections | 3/15/2021 | HANS SANTIAGO |
| Plan Check Approved | 4/7/2021 | ANDREW SANTIAGO |
| Issued | 6/16/2022 | APPLICANT |
| OK for CofC | 11/21/2022 | JOEY BUCHANAN |
| CofC Issued | 12/12/2022 | DAVID TSAU |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 3/15/2021 | MELISSA JONES |
| HPOZ | Cleared | 3/15/2021 | MELISSA JONES |
| Historic monument | Cleared | 3/15/2021 | MELISSA JONES |
| Specific Plan | Cleared | 3/16/2021 | MAXFIELD VERMY |
| Tenant Habitability Plan | Cleared | 6/15/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Retrofit 1; Lic. No.: 1003868-B | 19326 VENTURA BLVD STE 200 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/7/2022 | No Access for Inspection | GRANT WOODS |
| Pre-Inspection | 7/11/2022 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 8/4/2022 | No Access for Inspection | DERRICK SPENCER |
| Wood Frame | 8/4/2022 | No Access for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/5/2022 | Approved | GRANT WOODS |
| Wood Frame | 8/5/2022 | Approved | GRANT WOODS |
| Deputy Wood Construction | 8/24/2022 | Conditional Approval | GRANT WOODS |
| Structural Steel Frame | 9/8/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 9/8/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Structural Steel Frame | 9/12/2022 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 9/12/2022 | Partial Approval | GRANT WOODS |
| Wood Frame | 10/14/2022 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 10/21/2022 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 11/1/2022 | SGSOV Not Ready | PAUL DAVIDSON |
| Final | 11/16/2022 | No Access for Inspection | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Not Ready | PAUL DAVIDSON |
| Smoke Detectors | 11/16/2022 | No Access for Inspection | PAUL DAVIDSON |
| Final | 11/21/2022 | OK for CofC | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 11/21/2022 | Approved | JOEY BUCHANAN |