335 N VISTA ST 90036

Certificate Information: 335 N VISTA ST 90036

Application / Permit
20016-10000-15473
Plan Check / Job No.
B20LA11500
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE INTO ADU.
Permit Issued
Issued on 1/28/2021
Issuing Office
Current Status
CofO Issued on 2/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 JOE VO
Corrections Issued 7/28/2020 JOE VO
Quality Review Completed 8/3/2020 MINYE PAK
Applicant returned to address corrections 8/28/2020 JOE VO
Plan Check Approved 9/9/2020 JOE VO
Issued 1/28/2021 APPLICANT
CofO in Progress 3/1/2022 CHRIS CHRISTENSEN
Permit Finaled 2/23/2023 DANIEL ORRANTE
CofO Issued 2/23/2023 DANIEL ORRANTE
Permit Finaled 2/23/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/5/2020 WALLIE JONG
Sewer availability Cleared 8/5/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/10/2020 WALLIE JONG
Construction near power lines Cleared 12/24/2020 RIDWAN HARDY

Contact Information

Contractor Ofir Construction Inc; Lic. No.: 1036242-B 20641 SCHOOLCRAFT STREET      WINNETKA, CA 91306
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2021 Approved CHRIS CHRISTENSEN
Pre-Inspection 6/18/2021 Partial Approval JOSEPH MCGARRY
Pre-Inspection 10/6/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/28/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/28/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 10/28/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/5/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 11/5/2021 Approved CHRIS CHRISTENSEN
Insulation 11/5/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 11/5/2021 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 11/5/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 11/9/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/9/2021 Partial Approval CHRIS CHRISTENSEN
Final 1/31/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 1/31/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 1/31/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 2/11/2022 Approved CHRIS CHRISTENSEN
Final 2/11/2022 Conditional Approval CHRIS CHRISTENSEN
Green Building Final 2/11/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 2/11/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 2/11/2022 Approved CHRIS CHRISTENSEN
Final 2/28/2022 OK to Issue CofO CHRIS CHRISTENSEN