8709 S MCCONNELL AVE 90045
Certificate Information: 8709 S MCCONNELL AVE 90045
- Application / Permit
- 20016-10000-15471
- Plan Check / Job No.
- B20LA11498
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage into an ADU.
- Permit Issued
- Issued on 1/30/2021
- Issuing Office
- Current Status
- CofO Issued on 6/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | JOE VO |
| Corrections Issued | 7/28/2020 | JOE VO |
| Quality Review Completed | 8/3/2020 | MINYE PAK |
| Plan Check Approved | 1/20/2021 | JOE VO |
| Issued | 1/30/2021 | APPLICANT |
| CofO in Progress | 6/2/2022 | BOBBY KEY |
| Permit Finaled | 6/6/2022 | DANIEL ORRANTE |
| CofO Issued | 6/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2020 | SAUL GARCIA |
| Sewer availability | Cleared | 8/18/2020 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2020 | SAUL GARCIA |
| Construction near power lines | Cleared | 12/6/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Gaga Builders Inc; Lic. No.: 1038675-B | 22287 MULHOLLAND HWY UNIT #194 CALABASAS, CA 91302 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/17/2021 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 2/17/2021 | Approved | DAVID HEINE |
| Underground Mechanical | 2/17/2021 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 4/5/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 4/5/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 4/19/2021 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 4/19/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 4/19/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 4/19/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 4/28/2021 | Approved | BRENDAN LOONEY |
| Insulation | 4/28/2021 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 4/28/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Drywall Nailing | 5/3/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 5/10/2021 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 3/18/2022 | Approved | BOBBY KEY |
| Final | 3/18/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 3/18/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 3/18/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/18/2022 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 3/18/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/5/2022 | SGSOV Not Ready | BOBBY KEY |
| ELECTRICAL-Final | 4/8/2022 | Approved | BOBBY KEY |
| Final | 4/8/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 4/8/2022 | Approved | BOBBY KEY |
| HVAC-Final | 4/8/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 4/8/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Not Ready | BOBBY KEY |
| Final | 6/2/2022 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/2/2022 | SGSOV Approved | BOBBY KEY |