10141 S BEACH ST BLDG 29A 90002
Certificate Information: 10141 S BEACH ST BLDG 29A 90002
- Application / Permit
- 20016-10000-15385
- Plan Check / Job No.
- B20LA11428
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- REHAB OF 4 TOWNHOME APARTMENTS - ADD AN ACCESSIBLE BATHROOM AND BEDROOM TO THE GROUND FLOOR OF ONE UNIT. REHAB INCLUDES NEW DUAL GLAZED VINYL WINDOWS, NEW KITCHEN CABINETS AND APPLIANCES, NEW VINYL FLOORING, REPLACE TOILETS, SINKS AND FAUCETS REFINISH TUBS
- Permit Issued
- Issued on 6/14/2021
- Issuing Office
- Current Status
- CofO Issued on 6/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | AUNG SOE |
| Corrections Issued | 9/9/2020 | AUNG SOE |
| Quality Review Completed | 9/23/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 10/14/2020 | AUNG SOE |
| Applicant returned to address corrections | 10/21/2020 | AUNG SOE |
| Applicant returned to address corrections | 11/12/2020 | AUNG SOE |
| Green Plans Picked Up | 11/23/2020 | APPLICANT |
| Plan Check Approved | 5/25/2021 | AUNG SOE |
| Issued | 6/14/2021 | APPLICANT |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| CofO in Progress | 5/5/2023 | ALAN MORELOS |
| CofO Issued | 6/6/2023 | ERNESTO CORRAL |
| Permit Finaled | 6/6/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/7/2020 | JEANIE LAM |
| Sewer availability | Cleared | 10/7/2020 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 10/7/2020 | STEVEN HOFSTAD |
| ZA Case | Cleared | 10/8/2020 | KENTON TRINH |
| ZA Case | Cleared | 10/8/2020 | KENTON TRINH |
| ZA Case | Cleared | 10/8/2020 | KENTON TRINH |
| ZA Case | Cleared | 10/8/2020 | KENTON TRINH |
| ZA Case | Cleared | 10/8/2020 | KENTON TRINH |
| Metro Rail approval | Cleared | 10/13/2020 | AUNG SOE |
| Green Code | Cleared | 11/19/2020 | AUNG SOE |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | JEANIE LAM |
| DAS Clearance | Cleared | 1/5/2021 | AUNG SOE |
| Address approval | Cleared | 2/10/2021 | THOMAS LANG |
Contact Information
| Architect | Musser,, David Charles; Lic. No.: C15234 | 320 E GREENWOOD AVE LA HABRA, CA 90631 |
| Contractor | Portrait Construction Inc; Lic. No.: 977636-B | 265 N JOY STREET #200 CORONA, CA 92879 |
| Engineer | Wickstrom,, Eric Charles; Lic. No.: S3989 | 28581 VIA PIMAVERA SAN JUAN CAPISTRANO, CA 926755515 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/22/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Green Building Rough | 10/21/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/21/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/2/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 3/23/2023 | Not Ready for Inspection | ALAN MORELOS |
| Footing/Foundation/Slab | 3/23/2023 | Approved | ALAN MORELOS |
| Green Building Final | 3/23/2023 | Approved | ALAN MORELOS |
| Green Building Rough | 3/23/2023 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Approved | ALAN MORELOS |
| Smoke Detectors | 3/23/2023 | No Access for Inspection | ALAN MORELOS |
| Wood Frame | 3/23/2023 | Approved | ALAN MORELOS |
| Final | 5/5/2023 | OK to Issue CofO | ALAN MORELOS |
| Smoke Detectors | 5/5/2023 | Approved | ALAN MORELOS |