1721 E 103RD ST 90002
Certificate Information: 1721 E 103RD ST 90002
- Application / Permit
- 20016-10000-15337
- Plan Check / Job No.
- B20LA11428
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- REHAB OF 4 TOWNHOME APARTMENTS - ADD ACCESSIBLE BATHROOM AND BEDROOM AT THE GROUND FLOOR OF TWO UNITS. REHAB INCLUDES NEW DUAL GLAZED VINYL WINDOWS, NEW KITCHEN CABINETS AND APPLICANCES , NEW VINYL FLOORING, REPLACE TOILETS, SINKS AND FAUCETS REFINISH TUBS
- Permit Issued
- Issued on 6/14/2021
- Issuing Office
- Current Status
- CofO Issued on 6/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | AUNG SOE |
| Corrections Issued | 9/9/2020 | AUNG SOE |
| Quality Review Completed | 9/23/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 10/14/2020 | AUNG SOE |
| Applicant returned to address corrections | 10/21/2020 | AUNG SOE |
| Applicant returned to address corrections | 11/12/2020 | AUNG SOE |
| Green Plans Picked Up | 11/23/2020 | APPLICANT |
| Plan Check Approved | 5/25/2021 | AUNG SOE |
| Issued | 6/14/2021 | APPLICANT |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| CofO in Progress | 5/30/2023 | ALAN MORELOS |
| Permit Finaled | 6/8/2023 | ERNESTO CORRAL |
| CofO Issued | 6/8/2023 | ERNESTO CORRAL |
| Permit Finaled | 6/8/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/6/2020 | STEVEN HOFSTAD |
| Roof/Waste drainage to street | Cleared | 10/7/2020 | JEANIE LAM |
| Sewer availability | Cleared | 10/7/2020 | JEANIE LAM |
| ZA Case | Cleared | 10/8/2020 | KENTON TRINH |
| ZA Case | Cleared | 10/8/2020 | KENTON TRINH |
| ZA Case | Cleared | 10/8/2020 | KENTON TRINH |
| ZA Case | Cleared | 10/8/2020 | KENTON TRINH |
| ZA Case | Cleared | 10/8/2020 | KENTON TRINH |
| Metro Rail approval | Cleared | 10/13/2020 | AUNG SOE |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2020 | PAMELA TENEZA |
| DAS Clearance | Cleared | 1/5/2021 | AUNG SOE |
| Green Code | Cleared | 1/6/2021 | AUNG SOE |
| Address approval | Cleared | 2/10/2021 | THOMAS LANG |
Contact Information
| Architect | Musser,, David Charles; Lic. No.: C15234 | 320 E GREENWOOD AVE LA HABRA, CA 90631 |
| Contractor | Portrait Construction Inc; Lic. No.: 977636-B | 265 N JOY STREET #200 CORONA, CA 92879 |
| Engineer | Wickstrom,, Eric Charles; Lic. No.: S3989 | 28581 VIA PIMAVERA SAN JUAN CAPISTRANO, CA 926755515 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/31/2021 | No Access for Inspection | JOEY BUCHANAN |
| Pre-Inspection | 9/3/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Green Building Rough | 9/8/2021 | Approved | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 9/8/2021 | Approved | LEOPOLDO MENDOZA |
| Wood Frame | 9/8/2021 | Approved | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 4/1/2022 | Approved | RUSSELL BONVOULOIR |
| Deputy Wood Construction | 6/30/2022 | Conditional Approval | ERNESTO CORRAL |
| Final | 9/9/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 9/9/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Final | 9/9/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 9/9/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 9/9/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 3/23/2023 | Not Ready for Inspection | ALAN MORELOS |
| Final | 5/30/2023 | OK to Issue CofO | ALAN MORELOS |