3159 1/2 W WAVERLY DR 90027

Certificate Information: 3159 1/2 W WAVERLY DR 90027

Application / Permit
20016-10000-15281
Plan Check / Job No.
B20LA11390
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Conversion of existing detached garage into an ADU. Detached ADU per ordinance. Fire sprinkler system is provided.
Permit Issued
Issued on 10/2/2020
Issuing Office
Current Status
CofO Issued on 11/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2020 APPLICANT
Assigned to Plan Check Engineer 7/9/2020 HELEN NGUYEN
Corrections Issued 7/22/2020 HELEN NGUYEN
Quality Review Completed 7/29/2020 PRANITA SHAH
Applicant returned to address corrections 9/3/2020 HELEN NGUYEN
Applicant returned to address corrections 9/11/2020 HELEN NGUYEN
Applicant returned to address corrections 9/23/2020 HELEN NGUYEN
Plan Check Approved 10/1/2020 HELEN NGUYEN
Issued 10/2/2020 APPLICANT
CofO in Progress 11/20/2025 ENRIQUE MIRELES
Permit Finaled 11/22/2025 DEROLD HAUFF
CofO Issued 11/22/2025 DEROLD HAUFF
Permit Finaled 11/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/14/2020 ROSA SILVA
Grading Pre-Inspection Cleared 8/19/2020 PATRICK MISCHLICH
Sewer availability Cleared 8/25/2020 ROSA SILVA
Address approval Cleared 8/26/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 8/26/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Moradian,, Helbert; Lic. No.: C76618 6944 BECKETT STREET      TUJUNGA, CA 91042

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/14/2021 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 1/28/2021 Partial Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 2/17/2021 Partial Approval JOSEPH MCGARRY
Sewer 3/4/2021 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 3/4/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 3/22/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 5/26/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 5/26/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/7/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/7/2021 Partial Approval CHRIS CHRISTENSEN
Wood Frame 6/7/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/23/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 6/23/2021 Conditional Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/23/2021 Approved JOSEPH MCGARRY
Gas Test 6/23/2021 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 6/23/2021 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 6/23/2021 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 6/23/2021 Partial Approval JOSEPH MCGARRY
Insulation 8/19/2021 Partial Approval JOSEPH MCGARRY
Drywall Nailing 8/30/2021 Conditional Approval JOSEPH MCGARRY
Green Building Rough 8/30/2021 Approved JOSEPH MCGARRY
Shower Pan 9/7/2021 Approved JOSEPH MCGARRY
Gas Test 9/15/2021 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 9/15/2021 Approved CHARLES BOGHOSKHAN
Sewer 1/11/2023 Approved JOSEPH MCGARRY
Underground Mechanical 1/11/2023 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 5/9/2023 Approved JOSEPH MCGARRY
Drywall Nailing 5/9/2023 Approved JOSEPH MCGARRY
Final 5/9/2023 Corrections Issued JOSEPH MCGARRY
Green Building Final 5/9/2023 Approved JOSEPH MCGARRY
MERV13>=Final 5/9/2023 Approved JOSEPH MCGARRY
MERV13>=Rough 5/9/2023 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 5/9/2023 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 5/9/2023 Approved JOSEPH MCGARRY
Final 10/19/2023 Corrections Issued JOSEPH MCGARRY
Final 3/8/2024 Conditional Approval ENRIQUE MIRELES
Final 11/19/2025 OK to Issue CofO ENRIQUE MIRELES