1510 W 228TH ST 90501

Certificate Information: 1510 W 228TH ST 90501

Application / Permit
20016-10000-15250
Plan Check / Job No.
B20LA11368
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
INTERIOR TENANT IMPROVEMENTS TO (E) OFFICE AND WAREHOUSE. REMOVE PORTION OF (E) SECOND FLOOR. REMODEL (E) OFFICE. ADD (N) ROLL UP DOOR AND TRUCK DOCK. ADD (N) STOREFRONT. ADD (3) NEW DORMER SKYLIGHTS.
Permit Issued
Issued on 12/16/2020
Issuing Office
Current Status
CofO Issued on 7/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 KEVIN MORALES
Corrections Issued 7/29/2020 KEVIN MORALES
Quality Review Completed 8/3/2020 EUGENE BARBEAU
Disabled Access Plans Picked Up 8/25/2020 APPLICANT
Plan Check Approved 12/16/2020 KEVIN MORALES
Issued 12/16/2020 APPLICANT
Building Plans Picked Up 2/4/2021 APPLICANT
CofO in Progress 7/12/2021 JOEY BUCHANAN
CofO Issued 7/14/2021 NICK LAROCCA
Permit Finaled 7/14/2021 NICK LAROCCA

Permit Application Clearance Information

DAS Clearance Cleared 11/12/2020 KEVIN MORALES

Contact Information

Architect Lawrence,, Robert Louis; Lic. No.: C21447 3201A BROAD STREET      NEWPORT BEACH, CA 92663
Contractor Riat Construction Inc; Lic. No.: 956809-B P O BOX 129      RANCHO CUCAMONGA, CA 91739
Engineer Falamaki,, Mohsen; Lic. No.: S3021 344 N BUNDY DRIVE      LOS ANGELES, CA 90049

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/9/2021 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 2/9/2021 Partial Approval JOEY BUCHANAN
Pre-Inspection 2/9/2021 Approved JOEY BUCHANAN
Wood Frame 2/9/2021 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 3/26/2021 Conditional Approval JOEY BUCHANAN
Wood Frame 3/26/2021 Conditional Approval JOEY BUCHANAN
T-Bar Ceiling 5/25/2021 Approved NICK LAROCCA
Final 5/27/2021 Not Ready for Inspection JOEY BUCHANAN
METHANE-Final 5/27/2021 Approved JOEY BUCHANAN
METHANE-Rough 5/27/2021 Approved JOEY BUCHANAN
Reinforced Masonry Frame 5/27/2021 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 5/27/2021 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 5/27/2021 Approved JOEY BUCHANAN
Final 6/2/2021 Not Ready for Inspection NICK LAROCCA
Final 6/4/2021 Not Ready for Inspection JOEY BUCHANAN
Final 6/17/2021 Conditional Approval JOEY BUCHANAN