3200 E UNION PACIFIC AVE 90023

Certificate Information: 3200 E UNION PACIFIC AVE 90023

Application / Permit
20016-10000-15213
Plan Check / Job No.
B20LA11351
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Manufacturing
Work Description
REBUILD 5,437SF FIRE DAMAGED AREA OF (E) TWO STORY TYPE VB 19,919 SF STRUCTURE
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
Permit Finaled on 10/6/2021

Permit Application Status History

Submitted 6/26/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 JOHNNY WU
Corrections Issued 8/4/2020 JOHNNY WU
Quality Review Completed 8/12/2020 KESETE HAREGOT
Green Plans Picked Up 12/10/2020 APPLICANT
Applicant returned to address corrections 12/31/2020 JOHNNY WU
Applicant returned to address corrections 1/19/2021 JOHNNY WU
Plan Check Approved 1/19/2021 JOHNNY WU
Issued 4/12/2021 APPLICANT
Building Plans Picked Up 4/14/2021 APPLICANT
Permit Finaled 10/6/2021 DARRYL ARNOLD

Permit Application Clearance Information

Historic Resource Verification Cleared 9/2/2020 MICAELA TORRES-GIL
DAS Clearance Cleared 12/2/2020 JOHNNY WU
Green Code Cleared 12/8/2020 JOHNNY WU
Redevelopment Project Area Cleared 1/6/2021 DAVID URITA
ZI Cleared 1/15/2021 MAXFIELD VERMY
ZI Cleared 1/15/2021 MAXFIELD VERMY

Contact Information

Contractor M A C Builders; Lic. No.: 836368-B 14095 APPLE VALLEY ROAD      APPLE VALLEY, CA 92307
Engineer Fischer,, Kurt Mark; Lic. No.: S5432 PO BOX 809      POWAY, CA 92074

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 6/8/2021 Conditional Approval LANNY MERRICK
Wood Frame 6/11/2021 Not Ready for Inspection JONATHAN QUACH
Wood Frame 6/16/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 6/24/2021 Partial Approval LANNY MERRICK
Wood Frame 7/8/2021 Partial Approval MARK FERRARI
Final 8/24/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 8/24/2021 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 8/24/2021 SGSOV Not Ready LANNY MERRICK
Smoke Detectors 8/24/2021 Not Ready for Inspection LANNY MERRICK
Final 9/2/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 9/2/2021 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Not Ready LANNY MERRICK
Smoke Detectors 9/2/2021 Not Ready for Inspection LANNY MERRICK
Final 9/7/2021 Conditional Approval JONATHAN QUACH
Green Building Final 9/7/2021 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 9/7/2021 SGSOV Approved JONATHAN QUACH
Smoke Detectors 9/7/2021 Approved JONATHAN QUACH
Final 10/6/2021 Permit Finaled DARRYL ARNOLD