10225 W REGENT ST 90034
Certificate Information: 10225 W REGENT ST 90034
- Application / Permit
- 20016-10000-15207
- Plan Check / Job No.
- B20LA11337
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93 - INSTALL (2) STEEL SPECIAL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 9/30/2020
- Issuing Office
- Current Status
- CofC Issued on 2/8/2021
Permit Application Status History
| Submitted | 6/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | YOUNG KIM |
| Corrections Issued | 7/30/2020 | YOUNG KIM |
| Quality Review Completed | 7/31/2020 | SAI KHUM |
| Applicant returned to address corrections | 8/18/2020 | YOUNG KIM |
| Applicant returned to address corrections | 8/26/2020 | YOUNG KIM |
| Applicant returned to address corrections | 9/2/2020 | YOUNG KIM |
| Plan Check Approved | 9/11/2020 | YOUNG KIM |
| Issued | 9/30/2020 | APPLICANT |
| OK for CofC | 1/11/2021 | GRANT WOODS |
| CofC Issued | 2/8/2021 | TED RIES |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/22/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | R L G Construction; Lic. No.: 1023091-B | , |
| Engineer | Standley,, Craig Erick; Lic. No.: NA87675 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/21/2020 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 10/21/2020 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 10/23/2020 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 10/23/2020 | Partial Approval | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2020 | Approved | GRANT WOODS |
| Deputy Wood Construction | 10/29/2020 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 11/6/2020 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 11/12/2020 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 11/12/2020 | Approved | GRANT WOODS |
| Deputy Drilled-In Anchors | 11/13/2020 | Conditional Approval | GRANT WOODS |
| Final | 1/11/2021 | OK for CofC | GRANT WOODS |
| METHANE-Final | 1/11/2021 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 1/11/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 1/11/2021 | Approved | GRANT WOODS |