1111 S BROADWAY 90015

Certificate Information: 1111 S BROADWAY 90015

Application / Permit
20016-10000-14965
Plan Check / Job No.
B20LA11159
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Change of use from office to school.TI for partial levels 1 and 2 and entire level 3,4,5 of exsting building. Build out for primary office use with ancillary conference rooms, higher education classrooms on level 1 and level 2, and assembly flex space on level 1 with an adjacent catering pantry
Permit Issued
Issued on 9/21/2020
Issuing Office
Current Status
CofO Issued on 11/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2020 APPLICANT
Assigned to Plan Check Engineer 7/2/2020 LARRY LEE
Corrections Issued 7/8/2020 LARRY LEE
Quality Review Completed 7/14/2020 CHARLES CHANG
Building Plans Picked Up 7/14/2020 APPLICANT
Green Plans Picked Up 7/16/2020 APPLICANT
Applicant returned to address corrections 8/11/2020 LARRY LEE
Applicant returned to address corrections 8/25/2020 LARRY LEE
Applicant returned to address corrections 9/18/2020 LARRY LEE
Plan Check Approved 9/21/2020 LARRY LEE
Issued 9/21/2020 APPLICANT
TCO Issued (Expire Date: 02-02-2022) 8/6/2021 ERNESTO CORRAL
CofO in Progress 11/24/2021 KATY RAMIREZ
CofO Issued 11/24/2021 ERNESTO CORRAL
Permit Finaled 11/24/2021 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/30/2020 ELENA LOPEZ
City Hist. Cultural Monument Cleared 7/31/2020 LAMBERT GIESSINGER
Historic Resource Verification Cleared 7/31/2020 LAMBERT GIESSINGER
Historic monument Cleared 7/31/2020 LAMBERT GIESSINGER
Sewer availability Cleared 7/31/2020 ELENA LOPEZ
Food establishment approval Cleared 8/11/2020 LACDHS APPROVED
Redevelopment Project Area Cleared 8/11/2020 GISELLE CORELLA
CPC Cleared 8/13/2020 KENTON TRINH
ZA Case Cleared 8/13/2020 KENTON TRINH
ZA Case Cleared 8/13/2020 KENTON TRINH
ZA Case Cleared 8/13/2020 KENTON TRINH
Fire Marshall Fire Life Safety Cleared 9/15/2020 MENOA AGHAJANI
DAS Clearance Cleared 9/17/2020 LARRY LEE
Green Code Cleared 9/21/2020 VIVIAN LAO

Contact Information

Architect Sommerhalder, Olivier R; Lic. No.: C32170 844 GRANT #C      SANTA MONICA, CA 90405
Contractor Matt Construction Corporation; Lic. No.: 631020-B 9814 NORWALK BLVD #100      SANTA FE SPRINGS, CA 90670
Engineer Davis, Richard Hays; Lic. No.: C48082 2015 CANTATA DR      LOS ANGELES, CA 90068
Engineer Wilkerson, Ryan Lee; Lic. No.: S4728 20734 SARDINIA WAY      PORTER RANCH, CA 91326

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 10/7/2020 Partial Approval DANIEL COLLINS
Deputy Drilled-In Anchors 12/2/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 12/3/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 12/4/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/4/2020 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 12/4/2020 Partial Approval KATY RAMIREZ
Structural Steel Frame 12/4/2020 Not Ready for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 12/17/2020 Conditional Approval KATY RAMIREZ
Drywall Nailing 12/17/2020 No Access for Inspection KATY RAMIREZ
Light Gage Steel Frame 12/17/2020 Corrections Issued KATY RAMIREZ
Reinforced Concrete Frame 12/17/2020 No Access for Inspection KATY RAMIREZ
Drywall Nailing 12/21/2020 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 12/21/2020 Not Ready for Inspection KATY RAMIREZ
Reinforced Concrete Frame 12/21/2020 Partial Inspection KATY RAMIREZ
Structural Steel Frame 12/21/2020 Partial Inspection KATY RAMIREZ
Insulation 12/30/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/30/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 1/6/2021 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 1/6/2021 Partial Approval DANIEL COLLINS
Deputy Steel/Welding 1/20/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 1/21/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 1/22/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 1/25/2021 Conditional Approval RONALD PACHECO
Deputy Steel/Welding 1/26/2021 Conditional Approval KATY RAMIREZ
Insulation 2/4/2021 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 2/4/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/10/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 2/19/2021 Partial Inspection KATY RAMIREZ
Insulation 2/19/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/19/2021 Corrections Issued KATY RAMIREZ
Drywall Nailing 2/25/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/25/2021 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 3/2/2021 Partial Approval KATY RAMIREZ
Interior/Exterior Lathing 4/1/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 4/1/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 4/22/2021 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 5/13/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 5/19/2021 Partial Approval DANIEL COLLINS
T-Bar Ceiling 5/27/2021 Partial Approval DANIEL COLLINS
T-Bar Ceiling 6/8/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 6/10/2021 Partial Inspection KATY RAMIREZ
T-Bar Ceiling 6/14/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 6/17/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 6/24/2021 Partial Approval KATY RAMIREZ
Special/Order Compliance 7/1/2021 Not Ready for Inspection KATY RAMIREZ
T-Bar Ceiling 7/1/2021 Not Ready for Inspection KATY RAMIREZ
T-Bar Ceiling 7/2/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 7/6/2021 No Access for Inspection KATY RAMIREZ
T-Bar Ceiling 7/9/2021 Partial Approval KATY RAMIREZ
Special/Order Compliance 7/13/2021 Approved KATY RAMIREZ
Deputy Reinf. Concrete 7/14/2021 Conditional Approval KATY RAMIREZ
Special/Order Compliance 7/22/2021 Partial Approval DANIEL COLLINS
T-Bar Ceiling 7/22/2021 Partial Approval DANIEL COLLINS
Special/Order Compliance 7/28/2021 Partial Inspection KATY RAMIREZ
Final 8/4/2021 Partial Inspection KATY RAMIREZ
Green Building Final 8/4/2021 Partial Approval KATY RAMIREZ
Green Building Rough 8/4/2021 Approved KATY RAMIREZ
METHANE-Final 8/4/2021 Approved KATY RAMIREZ
METHANE-Rough 8/4/2021 Approved KATY RAMIREZ
Reinforced Masonry Frame 8/4/2021 Partial Approval KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Approved KATY RAMIREZ
Smoke Detectors 8/4/2021 Partial Approval KATY RAMIREZ
Special/Order Compliance 8/5/2021 Approved KATY RAMIREZ
Final 10/19/2021 Not Ready for Inspection KATY RAMIREZ
Green Building Final 10/19/2021 Approved KATY RAMIREZ
Reinforced Masonry Frame 10/19/2021 Not Ready for Inspection KATY RAMIREZ
Smoke Detectors 10/19/2021 Not Ready for Inspection KATY RAMIREZ
Final 11/9/2021 Not Ready for Inspection KATY RAMIREZ
Reinforced Masonry Frame 11/9/2021 Approved KATY RAMIREZ
Smoke Detectors 11/9/2021 Approved KATY RAMIREZ
Special/Order Compliance 11/12/2021 Approved KATY RAMIREZ
Special/Order Compliance 11/15/2021 Approved KATY RAMIREZ
Final 11/22/2021 Partial Inspection KATY RAMIREZ
Final 11/24/2021 OK to Issue CofO KATY RAMIREZ