4580 W ELECTRONICS PL 90039
Certificate Information: 4580 W ELECTRONICS PL 90039
- Application / Permit
- 20016-10000-14931
- Plan Check / Job No.
- B20LA11116
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Eplan. Tenant improvement of existing office space to create (2) new lab rooms, (1) new microscopy room and open work area.
- Permit Issued
- Issued on 11/13/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/9/2022
Permit Application Status History
| Submitted | 7/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2020 | HELEN NGUYEN |
| Corrections Issued | 7/21/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 8/28/2020 | HELEN NGUYEN |
| Plan Check Approved | 9/2/2020 | MONICA RAMIREZ |
| Issued | 11/13/2020 | APPLICANT |
| Permit Finaled | 5/6/2022 | JONATHAN QUACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Shen,, Perry Po-Li; Lic. No.: C21154 | 14469 MERCED AVE BALDWIN PARK, CA 91706 |
| Contractor | Kaiser Foundation Health Plan Inc; Lic. No.: 370871-B | 4175 E LA PALMA AVE STE 200 ANAHEIM, CA 92807 |
| Engineer | Huang,, Yaw-Kai; Lic. No.: S2062 | 1414 OXFORD RD SAN MARINO, CA 91108 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/14/2020 | Approved | EDWIN GREGORYONA |
| Light Gage Steel Frame | 12/28/2020 | Approved | EDWIN GREGORYONA |
| Wood Frame | 12/28/2020 | Approved | EDWIN GREGORYONA |
| Insulation | 12/29/2020 | Approved | EDWIN GREGORYONA |
| T-Bar Ceiling | 2/9/2021 | Partial Approval | EDWIN GREGORYONA |
| Final | 2/12/2021 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 3/8/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 3/8/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 3/12/2021 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 5/18/2021 | Approved | EDWIN GREGORYONA |
| Structural Steel Frame | 5/18/2021 | Approved | EDWIN GREGORYONA |
| Wall Anchors | 5/18/2021 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 6/1/2021 | Approved | RUSSELL BONVOULOIR |
| Insulation | 6/1/2021 | Approved | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 8/30/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Light Gage Steel Frame | 8/31/2021 | Partial Approval | DANIEL COLLINS |
| Special/Order Compliance | 11/5/2021 | Partial Inspection | SORIN CIRSTOIU |
| Final | 5/6/2022 | Permit Finaled | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 5/6/2022 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 5/6/2022 | Approved | JONATHAN QUACH |