826 W 71ST ST 90044
Certificate Information: 826 W 71ST ST 90044
- Application / Permit
- 20016-10000-14810
- Plan Check / Job No.
- B20LA11013
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADUS. Convert Existing Single Car garage into an accessory dwelling unit per ordinance. Scope will also include a 89.4 sqft addition . All work per WFPP.
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Current Status
- CofO Issued on 11/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | MICHAEL LOPEZ |
| Corrections Issued | 7/10/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 7/21/2020 | PRANITA SHAH |
| Plan Check Approved | 10/21/2020 | MICHAEL LOPEZ |
| Issued | 4/12/2021 | APPLICANT |
| CofO in Progress | 10/31/2023 | MICHAEL LEWIS |
| CofO Issued | 11/3/2023 | DEROLD HAUFF |
| Permit Finaled | 11/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2020 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/28/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 10/21/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/20/2021 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/8/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/11/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 12/13/2022 | No Access for Inspection | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 12/20/2022 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 12/27/2022 | Partial Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/31/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/2/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/9/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/20/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/20/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 3/20/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 3/20/2023 | Approved | STUART CHAPMAN |
| Insulation | 3/30/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/30/2023 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 4/5/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/5/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/27/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 4/27/2023 | Approved | MICHAEL LEWIS |
| Sewer | 5/3/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 5/3/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/20/2023 | Approved | MICHAEL LEWIS |
| Final | 6/20/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 6/20/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/20/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 6/20/2023 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 6/20/2023 | Approved | MICHAEL LEWIS |
| Final | 9/14/2023 | Partial Inspection | MICHAEL LEWIS |
| Final | 10/27/2023 | No Access for Inspection | CRAIG DAVIS |
| Final | 10/30/2023 | OK to Issue CofO | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 10/30/2023 | Approved | MICHAEL LEWIS |