9844 N HASKELL AVE 91343

Certificate Information: 9844 N HASKELL AVE 91343

Application / Permit
20016-10000-14807
Plan Check / Job No.
B20LA11010
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADUs. CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 8/28/2020
Issuing Office
Current Status
CofO Issued on 9/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 MICHAEL LOPEZ
Corrections Issued 7/9/2020 MICHAEL LOPEZ
Quality Review Completed 7/21/2020 PRANITA SHAH
Plan Check Approved 8/24/2020 MICHAEL LOPEZ
Issued 8/28/2020 APPLICANT
CofO in Progress 9/14/2022 JENNIFER RABUCHIN
Permit Finaled 9/22/2022 MICHAEL SMITH
CofO Issued 9/22/2022 MICHAEL SMITH
Permit Finaled 9/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/13/2020 ADRIAN CASTRO
Sewer availability Cleared 7/13/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/14/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/2/2020 Corrections Issued MISAEL ESPARZA
Underground Mechanical 9/8/2020 Approved DAVID SCANTLIN
Footing/Foundation/Slab 9/21/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 10/21/2020 Not Ready for Inspection MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 10/21/2020 Partial Approval MICHAEL TEMPLE
MERV13>=Rough 10/21/2020 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Rough 10/21/2020 Not Ready for Inspection MICHAEL TEMPLE
ELECTRICAL-Rough 11/5/2020 Partial Approval ARTHUR SARGSYAN
Interior/Exterior Lathing 11/5/2020 Partial Approval ARTHUR SARGSYAN
PLUMBING-Rough 11/5/2020 Approved ARTHUR SARGSYAN
Wood Frame 11/5/2020 Approved ARTHUR SARGSYAN
Insulation 11/13/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 11/20/2020 Approved ARTHUR SARGSYAN
Shower Pan 12/2/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/5/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 1/5/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 1/5/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Rough 1/5/2021 Not Ready for Inspection ARTHUR SARGSYAN
MERV13>=Final 1/5/2021 Not Ready for Inspection ARTHUR SARGSYAN
MERV13>=Rough 1/5/2021 Approved ARTHUR SARGSYAN
Pre-Inspection 1/5/2021 No Access for Inspection MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 1/5/2021 SGSOV Approved ARTHUR SARGSYAN
Service/Power Release 1/5/2021 Corrections Issued ARTHUR SARGSYAN
Smoke Detectors 1/5/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/12/2021 Approved JENNIFER RABUCHIN
Final 1/12/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/12/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 1/12/2021 Approved JENNIFER RABUCHIN
MERV13>=Final 1/12/2021 Approved JENNIFER RABUCHIN
Smoke Detectors 1/12/2021 Approved JENNIFER RABUCHIN
Final 9/15/2022 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 9/15/2022 Approved JENNIFER RABUCHIN
HVAC-Final 9/15/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/15/2022 Approved JENNIFER RABUCHIN