4410 W CLINTON ST 90004
Certificate Information: 4410 W CLINTON ST 90004
- Application / Permit
- 20016-10000-14778
- Plan Check / Job No.
- B20LA10990
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL SPECIAL STEEL CANTILEVER COLUMN
- Permit Issued
- Issued on 7/7/2021
- Issuing Office
- Current Status
- CofC Issued on 11/1/2021
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2020 | HANS SANTIAGO |
| Corrections Issued | 7/20/2020 | HANS SANTIAGO |
| Quality Review Completed | 7/22/2020 | SAI KHUM |
| Building Plans Picked Up | 7/24/2020 | APPLICANT |
| Plan Check Approved | 3/29/2021 | ANDREW SANTIAGO |
| Plan Check Approved | 3/31/2021 | ANDREW SANTIAGO |
| Issued | 7/7/2021 | APPLICANT |
| OK for CofC | 10/27/2021 | BRUCE CAMPBELL |
| CofC Issued | 11/1/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 7/7/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 7/26/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Other (see comments) | 7/26/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 7/26/2021 | Conditional Approval | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 7/28/2021 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 7/28/2021 | Not Ready for Inspection | BRUCE CAMPBELL |
| Wood Frame | 7/28/2021 | Not Ready for Inspection | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 7/29/2021 | Conditional Approval | FRED WOHLFARTH |
| Structural Steel Frame | 8/2/2021 | Approved | BRUCE CAMPBELL |
| Wood Frame | 8/2/2021 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 9/15/2021 | Partial Approval | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 9/27/2021 | Corrections Issued | BRUCE CAMPBELL |
| Final | 10/27/2021 | OK for CofC | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 10/27/2021 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 10/27/2021 | Approved | BRUCE CAMPBELL |