916 1/2 E IMPERIAL HWY 90059

Certificate Information: 916 1/2 E IMPERIAL HWY 90059

Application / Permit
20016-10000-14551
Plan Check / Job No.
B20LA10833
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADUs. Conversion of (E) 2-car garage into an ADU. Detached ADU per ordinance.
Permit Issued
Issued on 1/27/2021
Issuing Office
Current Status
CofO Issued on 1/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 HELEN NGUYEN
Corrections Issued 7/13/2020 HELEN NGUYEN
Quality Review Completed 7/21/2020 PRANITA SHAH
Applicant returned to address corrections 8/10/2020 HELEN NGUYEN
Applicant returned to address corrections 11/12/2020 HELEN NGUYEN
Applicant returned to address corrections 12/2/2020 HELEN NGUYEN
Plan Check Approved 12/31/2020 HELEN NGUYEN
Issued 1/27/2021 APPLICANT
Building Plans Picked Up 2/2/2021 APPLICANT
CofO in Progress 1/21/2022 ALIZAH MAYAGOITIA
Permit Finaled 1/22/2022 DEROLD HAUFF
CofO Issued 1/22/2022 DEROLD HAUFF
Permit Finaled 1/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 10/8/2020 HELEN JADALI
Address approval Cleared 10/23/2020 CECILIO NAVARRO
Sewer availability Cleared 10/23/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/28/2020 CECILIO NAVARRO
Tenant Habitability Plan Cleared 12/8/2020 STEVEN HOFSTAD

Contact Information

Architect Best,, Richard Allen; Lic. No.: C17334 1275 BEVERLY ESTATES DR.      BEVERLY HILLS, CA 90210
Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/27/2021 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 7/20/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 7/20/2021 Partial Approval EUGENE CASSIDY
Sewer 7/20/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 8/2/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 8/2/2021 Approved EUGENE CASSIDY
Sewer 8/2/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/18/2021 Corrections Issued CRAIG DAVIS
MERV13>=Rough 10/18/2021 Not Ready for Inspection CRAIG DAVIS
Rough-Elec/Plmb/HVAC 10/18/2021 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 10/21/2021 Approved EUGENE CASSIDY
Wood Frame 10/21/2021 Approved EUGENE CASSIDY
Insulation 10/28/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/28/2021 Partial Approval EUGENE CASSIDY
Drywall Nailing 11/2/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/8/2021 Approved EUGENE CASSIDY
Shower Pan 12/8/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 1/11/2022 Approved EUGENE CASSIDY
Final 1/11/2022 Corrections Issued EUGENE CASSIDY
MERV13>=Final 1/11/2022 Approved EUGENE CASSIDY
MERV13>=Rough 1/11/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/11/2022 SGSOV Approved EUGENE CASSIDY
Service/Power Release 1/11/2022 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 1/11/2022 Approved EUGENE CASSIDY
Final 1/20/2022 Conditional Approval ALIZAH MAYAGOITIA
Final 1/21/2022 OK to Issue CofO ALIZAH MAYAGOITIA