916 1/2 E IMPERIAL HWY 90059
Certificate Information: 916 1/2 E IMPERIAL HWY 90059
- Application / Permit
- 20016-10000-14551
- Plan Check / Job No.
- B20LA10833
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADUs. Conversion of (E) 2-car garage into an ADU. Detached ADU per ordinance.
- Permit Issued
- Issued on 1/27/2021
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | HELEN NGUYEN |
| Corrections Issued | 7/13/2020 | HELEN NGUYEN |
| Quality Review Completed | 7/21/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 8/10/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 11/12/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/2/2020 | HELEN NGUYEN |
| Plan Check Approved | 12/31/2020 | HELEN NGUYEN |
| Issued | 1/27/2021 | APPLICANT |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| CofO in Progress | 1/21/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
| CofO Issued | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 10/8/2020 | HELEN JADALI |
| Address approval | Cleared | 10/23/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/23/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2020 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 12/8/2020 | STEVEN HOFSTAD |
Contact Information
| Architect | Best,, Richard Allen; Lic. No.: C17334 | 1275 BEVERLY ESTATES DR. BEVERLY HILLS, CA 90210 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/27/2021 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 7/20/2021 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 7/20/2021 | Partial Approval | EUGENE CASSIDY |
| Sewer | 7/20/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/2/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/2/2021 | Approved | EUGENE CASSIDY |
| Sewer | 8/2/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/18/2021 | Corrections Issued | CRAIG DAVIS |
| MERV13>=Rough | 10/18/2021 | Not Ready for Inspection | CRAIG DAVIS |
| Rough-Elec/Plmb/HVAC | 10/18/2021 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2021 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 10/21/2021 | Approved | EUGENE CASSIDY |
| Wood Frame | 10/21/2021 | Approved | EUGENE CASSIDY |
| Insulation | 10/28/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/28/2021 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 11/2/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/8/2021 | Approved | EUGENE CASSIDY |
| Shower Pan | 12/8/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/11/2022 | Approved | EUGENE CASSIDY |
| Final | 1/11/2022 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Final | 1/11/2022 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 1/11/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/11/2022 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 1/11/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 1/11/2022 | Approved | EUGENE CASSIDY |
| Final | 1/20/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 1/21/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |