2031 W 29TH PL 90018
Certificate Information: 2031 W 29TH PL 90018
- Application / Permit
- 20016-10000-14550
- Plan Check / Job No.
- B20LA10832
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 8/17/2020
- Issuing Office
- Current Status
- CofO Issued on 4/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2020 | LAMAR DAVIS |
| Corrections Issued | 7/1/2020 | LAMAR DAVIS |
| Quality Review Completed | 7/8/2020 | TU HUA |
| Applicant returned to address corrections | 7/14/2020 | LAMAR DAVIS |
| Plan Check Approved | 8/11/2020 | LAMAR DAVIS |
| Issued | 8/17/2020 | APPLICANT |
| CofO in Progress | 12/24/2020 | ROBERT MCDOWELL |
| Permit Finaled | 4/18/2021 | DEROLD HAUFF |
| CofO Issued | 4/18/2021 | DEROLD HAUFF |
| Permit Finaled | 4/18/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2020 | CECILIO NAVARRO |
| HPOZ | Cleared | 7/13/2020 | MAX LODER |
| Miscellaneous | Cleared | 7/13/2020 | MAX LODER |
| Sewer availability | Cleared | 7/13/2020 | CECILIO NAVARRO |
| ZI | Cleared | 7/13/2020 | MAX LODER |
Contact Information
| Contractor | G A Design Build; Lic. No.: 941130-B | 8449 EVERST ST DOWNEY, CA 90242 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 8/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Rough | 8/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| PLUMBING-Rough | 8/20/2020 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 8/20/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 8/26/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 8/26/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 8/26/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Rough | 8/26/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 8/31/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 8/31/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 9/4/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 11/23/2020 | No Access for Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Final | 11/23/2020 | No Access for Inspection | ROBERT MCDOWELL |
| Final | 11/23/2020 | No Access for Inspection | ROBERT MCDOWELL |
| Green Building Final | 11/23/2020 | No Access for Inspection | ROBERT MCDOWELL |
| Green Building Rough | 11/23/2020 | No Access for Inspection | ROBERT MCDOWELL |
| HVAC-Final | 11/23/2020 | No Access for Inspection | ROBERT MCDOWELL |
| PLUMBING-Final | 11/23/2020 | No Access for Inspection | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 11/23/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 11/23/2020 | No Access for Inspection | ROBERT MCDOWELL |
| Smoke Detectors | 11/23/2020 | No Access for Inspection | ROBERT MCDOWELL |
| Service/Power Release | 12/1/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 12/7/2020 | Approved | FREDDIE RIVERA |
| Final | 12/7/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 12/7/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/7/2020 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 12/7/2020 | Approved | FREDDIE RIVERA |
| Service/Power Release | 12/11/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 12/24/2020 | Approved | ROBERT MCDOWELL |
| Final | 12/24/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| HVAC-Final | 12/24/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 12/24/2020 | Approved | ROBERT MCDOWELL |