3226 S PHILO ST 90064
Certificate Information: 3226 S PHILO ST 90064
- Application / Permit
- 20016-10000-14503
- Plan Check / Job No.
- B20LA10790
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- REDUCE THE SIZE OF THE (E) STORAGE BUILDING
- Permit Issued
- Issued on 7/23/2020
- Issuing Office
- Current Status
- CofO Issued on 1/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2020 | FERNANDO FLORES |
| Corrections Issued | 6/23/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 7/8/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/21/2020 | AUNG SOE |
| Plan Check Approved | 7/23/2020 | AUNG SOE |
| Issued | 7/23/2020 | APPLICANT |
| Building Plans Picked Up | 8/31/2020 | APPLICANT |
| CofO in Progress | 11/16/2020 | KEVIN SARGSYAN |
| No Progress | 12/4/2020 | KENNETH NAGLE |
| CofO in Progress | 1/7/2021 | KENNETH NAGLE |
| Permit Finaled | 1/19/2021 | KENNETH NAGLE |
| CofO Issued | 1/19/2021 | KENNETH NAGLE |
| Permit Finaled | 1/19/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2020 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 7/7/2020 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 7/13/2020 | KIRK LINKLATER |
| Construction near power lines | Cleared | 7/14/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | R K Industries Group Inc; Lic. No.: 996175-B | 3000 S SAWGRASS COURT LA HABRA, CA 90631 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/2/2020 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2020 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/1/2020 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 10/5/2020 | Approved | KEVIN SARGSYAN |
| Insulation | 10/5/2020 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/27/2020 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/27/2020 | Approved | KEVIN SARGSYAN |
| Final | 10/27/2020 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2020 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 10/27/2020 | Approved | KEVIN SARGSYAN |
| Final | 11/16/2020 | OK to Issue CofO | KEVIN SARGSYAN |