14949 W ROSCOE BLVD 91402

Certificate Information: 14949 W ROSCOE BLVD 91402

Application / Permit
20016-10000-14467
Plan Check / Job No.
B20LA10755
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT ATTACHED GARAGE & STORAGE AREA IN A N EXISTING 25 UNIT APARTMENT BUILDING TO 6 NEW ACCESSORY DWELLING UNITS PER CA GCS 65852.2(e)(1)(C) (Existing parking per 20016-10000-02684)
Permit Issued
Issued on 1/25/2021
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 PRANITA SHAH
Corrections Issued 7/27/2020 PRANITA SHAH
Quality Review Completed 8/17/2020 MINYE PAK
Building Plans Picked Up 8/19/2020 APPLICANT
Green Plans Picked Up 9/2/2020 APPLICANT
Applicant returned to address corrections 10/5/2020 PRANITA SHAH
Applicant returned to address corrections 12/4/2020 PRANITA SHAH
Plan Check Approved 12/28/2020 PRANITA SHAH
Issued 1/25/2021 APPLICANT
CofO in Progress 8/1/2022 ANDREW DORSO
CofO Issued 8/2/2022 JEFFREY DURAN
Permit Finaled 8/2/2022 JEFFREY DURAN

Permit Application Clearance Information

Sewer availability Cleared 8/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/25/2020 ADRIAN CASTRO
ZA Case Cleared 8/28/2020 KENTON TRINH
Green Code Cleared 9/1/2020 KHEDER ALRAZAA
Fire Marshall Fire Life Safety Cleared 11/23/2020 ANDREW KO

Contact Information

Architect Moss,, Kyle A; Lic. No.: C28077 2627 30TH STREET      SANTA MONICA, CA 90405
Contractor Stay Forever Construction Corporation; Lic. No.: 986055-B 27138 CHERRY LAUREL PL      CANYON COUNTRY, CA 91387
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 3/1/2021 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 5/20/2021 Conditional Approval ANDREW DORSO
Drywall Nailing 6/28/2021 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 7/16/2021 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 8/20/2021 Approved ANDREW DORSO
Insulation 8/20/2021 Corrections Issued ANDREW DORSO
Insulation 11/17/2021 Partial Inspection ANDREW DORSO
Deputy Wood Construction 12/3/2021 Conditional Approval ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 12/23/2021 Partial Inspection ANDREW DORSO
Insulation 1/25/2022 Approved ANDREW DORSO
Wood Frame 1/25/2022 Approved ANDREW DORSO
Drywall Nailing 1/28/2022 Approved ANDREW DORSO
Interior/Exterior Lathing 1/28/2022 Approved ANDREW DORSO
Final 7/19/2022 Not Ready for Inspection ANDREW DORSO
Green Building Final 7/19/2022 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Approved ANDREW DORSO
Smoke Detectors 7/19/2022 Not Ready for Inspection ANDREW DORSO
Final 7/27/2022 OK to Issue CofO ANDREW DORSO
Smoke Detectors 7/27/2022 Approved ANDREW DORSO