2927-2929 S HALLDALE AVE 90018
Certificate Information: 2927-2929 S HALLDALE AVE 90018
- Application / Permit
- 20016-10000-14441
- Plan Check / Job No.
- B20LA10729
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERSION OF AN EXISTING 479 SF ATTACHED GARAGE INTO A 61 SF STORAGE AREA AND 405 SF ADU TO (E) SFD
- Permit Issued
- Issued on 8/27/2020
- Issuing Office
- Current Status
- CofO Issued on 6/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2020 | FERNANDO FLORES |
| Corrections Issued | 6/23/2020 | FERNANDO FLORES |
| Plan Check Approved | 8/13/2020 | FERNANDO FLORES |
| Issued | 8/27/2020 | APPLICANT |
| Building Plans Picked Up | 10/5/2020 | APPLICANT |
| CofO in Progress | 3/22/2021 | KATHRYN BUTTERWORTH |
| No Progress | 4/13/2022 | SCOTT FINNILA |
| CofO in Progress | 4/25/2022 | KATHRYN BUTTERWORTH |
| Permit Finaled | 6/23/2022 | DEROLD HAUFF |
| CofO Issued | 6/23/2022 | DEROLD HAUFF |
| Permit Finaled | 6/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 7/20/2020 | RENZ SORIANO |
| Community Plan Implem. Overlay | Cleared | 7/27/2020 | RAFAEL FONTES |
Contact Information
| Contractor | G D Z Inc; Lic. No.: 631186-B | PO BOX 160 SUNLAND, CA 91041 |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2020 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Rough | 11/4/2020 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 11/10/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/10/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/8/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 12/8/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Rough | 12/8/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 12/24/2020 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 12/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 12/30/2020 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 12/30/2020 | Approved | SCOTT FINNILA |
| Shower Pan | 12/30/2020 | Approved | SCOTT FINNILA |
| Final | 3/11/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 3/11/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 3/11/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 3/11/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 3/22/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 4/14/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 4/25/2022 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 6/6/2022 | Corrections Issued | KATHRYN BUTTERWORTH |