2927-2929 S HALLDALE AVE 90018

Certificate Information: 2927-2929 S HALLDALE AVE 90018

Application / Permit
20016-10000-14441
Plan Check / Job No.
B20LA10729
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF AN EXISTING 479 SF ATTACHED GARAGE INTO A 61 SF STORAGE AREA AND 405 SF ADU TO (E) SFD
Permit Issued
Issued on 8/27/2020
Issuing Office
Current Status
CofO Issued on 6/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2020 APPLICANT
Assigned to Plan Check Engineer 6/23/2020 FERNANDO FLORES
Corrections Issued 6/23/2020 FERNANDO FLORES
Plan Check Approved 8/13/2020 FERNANDO FLORES
Issued 8/27/2020 APPLICANT
Building Plans Picked Up 10/5/2020 APPLICANT
CofO in Progress 3/22/2021 KATHRYN BUTTERWORTH
No Progress 4/13/2022 SCOTT FINNILA
CofO in Progress 4/25/2022 KATHRYN BUTTERWORTH
Permit Finaled 6/23/2022 DEROLD HAUFF
CofO Issued 6/23/2022 DEROLD HAUFF
Permit Finaled 6/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/16/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/20/2020 RENZ SORIANO
Sewer availability Cleared 7/20/2020 RENZ SORIANO
Community Plan Implem. Overlay Cleared 7/27/2020 RAFAEL FONTES

Contact Information

Contractor G D Z Inc; Lic. No.: 631186-B PO BOX 160      SUNLAND, CA 91041
Engineer Basso,, Alexandre; Lic. No.: C77670 7231 SUMMITROSE ST      TUJUNGA, CA 91042

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2020 Corrections Issued RUBEN SALAS
PLUMBING-Rough 11/4/2020 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 11/10/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 11/10/2020 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 12/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Rough 12/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/14/2020 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 12/14/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 12/14/2020 Approved KATHRYN BUTTERWORTH
METHANE-Rough 12/14/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 12/14/2020 Approved KATHRYN BUTTERWORTH
Insulation 12/24/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 12/24/2020 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 12/30/2020 Approved SCOTT FINNILA
Interior/Exterior Lathing 12/30/2020 Approved SCOTT FINNILA
Shower Pan 12/30/2020 Approved SCOTT FINNILA
Final 3/11/2021 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 3/11/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 3/11/2021 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 3/11/2021 Approved KATHRYN BUTTERWORTH
Final 3/22/2021 OK to Issue CofO KATHRYN BUTTERWORTH
Special/Order Compliance 4/14/2022 Corrections Issued KATHRYN BUTTERWORTH
Final 4/25/2022 OK to Issue CofO KATHRYN BUTTERWORTH
Special/Order Compliance 6/6/2022 Corrections Issued KATHRYN BUTTERWORTH