2123 1/2 S ORANGE DR 90016

Certificate Information: 2123 1/2 S ORANGE DR 90016

Application / Permit
20016-10000-14434
Plan Check / Job No.
B20LA10722
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING ATTACHED GARAGE TO ADU PER CA GOVT. CODE 65852.2 (e)(1)(A).
Permit Issued
Issued on 2/17/2021
Issuing Office
Current Status
CofO Issued on 10/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 MAHNAZ NOURHASHEMI
Corrections Issued 7/10/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 7/17/2020 TIEN JEN WANG
Building Plans Picked Up 9/1/2020 APPLICANT
Green Plans Picked Up 10/5/2020 APPLICANT
Applicant returned to address corrections 10/15/2020 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 2/2/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 2/10/2021 MAHNAZ NOURHASHEMI
Issued 2/17/2021 APPLICANT
CofO in Progress 10/18/2021 TIMOTHY BUXTON
Permit Finaled 10/18/2021 ERNESTO CORRAL
CofO Issued 10/18/2021 ERNESTO CORRAL
Permit Finaled 10/18/2021 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 9/29/2020 KHEDER ALRAZAA
Eng Process Fee Ord 176,300 Cleared 10/30/2020 RENZ SORIANO
Address approval Cleared 12/14/2020 CELINA MORENO
Sewer availability Cleared 12/14/2020 CELINA MORENO
Tenant Habitability Plan Cleared 1/8/2021 PHILLIP MUNGUIA
Hydrant and Access approval Cleared 1/11/2021 MATTHEW CRAIG
Construction near power lines Cleared 2/5/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/23/2021 Approved TIMOTHY BUXTON
Footing/Foundation/Slab 3/23/2021 Approved TIMOTHY BUXTON
Green Building Rough 5/3/2021 Approved TIMOTHY BUXTON
Wood Frame 5/3/2021 Not Ready for Inspection TIMOTHY BUXTON
Interior/Exterior Lathing 5/11/2021 Approved TIMOTHY BUXTON
Wood Frame 5/11/2021 Not Ready for Inspection TIMOTHY BUXTON
Insulation 6/11/2021 Approved TIMOTHY BUXTON
Drywall Nailing 6/15/2021 Approved TIMOTHY BUXTON
Interior/Exterior Lathing 6/21/2021 Approved JONATHAN QUACH
Final 10/5/2021 Not Ready for Inspection SORIN CIRSTOIU
Green Building Final 10/5/2021 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 10/5/2021 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 10/5/2021 Not Ready for Inspection SORIN CIRSTOIU
Wood Frame 10/5/2021 Not Ready for Inspection SORIN CIRSTOIU
Final 10/15/2021 Conditional Approval TIMOTHY BUXTON
Green Building Final 10/15/2021 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 10/15/2021 SGSOV Approved TIMOTHY BUXTON
Smoke Detectors 10/15/2021 Approved TIMOTHY BUXTON
Wood Frame 10/15/2021 Approved TIMOTHY BUXTON