3224 W ATWATER AVE 90039

Certificate Information: 3224 W ATWATER AVE 90039

Application / Permit
20016-10000-14418
Plan Check / Job No.
B20LA10690
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADUs. Convert existing detached garage into an Accessory dwelling Unit per ordinance. Scope will also include a irregualr (20'-2"x 24'-7") addition to create a covered patio.
Permit Issued
Issued on 9/23/2020
Issuing Office
Current Status
CofO Issued on 4/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 6/25/2020 MICHAEL LOPEZ
Corrections Issued 7/1/2020 MICHAEL LOPEZ
Quality Review Completed 7/10/2020 PRANITA SHAH
Plan Check Approved 9/10/2020 MICHAEL LOPEZ
Issued 9/23/2020 APPLICANT
CofO in Progress 3/24/2022 HAMIK HARTOUNIAN
Permit Finaled 4/13/2022 DEROLD HAUFF
CofO Issued 4/13/2022 DEROLD HAUFF
Permit Finaled 4/13/2022 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 8/3/2020 TERRI OSBORNE
Address approval Cleared 8/10/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/10/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 8/10/2020 CECILIO NAVARRO
Sewer availability Cleared 8/10/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Tuchscher,, James Todd; Lic. No.: NA77649       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/1/2021 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 3/30/2021 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/31/2021 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/31/2021 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 4/1/2021 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/9/2021 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/20/2021 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 4/20/2021 Partial Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 5/20/2021 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/9/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/9/2021 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/9/2021 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/9/2021 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 6/9/2021 Approved HAMIK HARTOUNIAN
Sewer 6/9/2021 Conditional Approval HAMIK HARTOUNIAN
Gas Test 8/11/2021 Approved CHARLES BOGHOSKHAN
Insulation 8/11/2021 Approved CHARLES BOGHOSKHAN
Deputy Wood Construction 8/16/2021 Conditional Approval CHARLES BOGHOSKHAN
Drywall Nailing 10/15/2021 Approved HAMIK HARTOUNIAN
Shower Pan 10/15/2021 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/18/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/17/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 3/17/2022 Approved HAMIK HARTOUNIAN
Final 3/17/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/17/2022 Approved HAMIK HARTOUNIAN
Gas Test 3/17/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 3/17/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 3/17/2022 Approved HAMIK HARTOUNIAN
HVAC-Final 3/17/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 3/17/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 3/17/2022 Approved HAMIK HARTOUNIAN
Final 3/23/2022 OK to Issue CofO HAMIK HARTOUNIAN
Gas Test 3/23/2022 Approved HAMIK HARTOUNIAN
Green Building Final 3/23/2022 Approved HAMIK HARTOUNIAN