7761 N ARCOLA AVE 91352

Certificate Information: 7761 N ARCOLA AVE 91352

Application / Permit
20016-10000-14221
Plan Check / Job No.
B20LA10579
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 25'-5"X20'-3 1/2" TO AND CONVERT THE EXISTING 20'-3'X20'-3 1/2" GARAGE INTO AN ACCESSORY DWELING UNIT. WORK WORK WFPP.
Permit Issued
Issued on 8/10/2020
Issuing Office
Current Status
CofO Issued on 3/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 JOHNNY WU
Corrections Issued 6/18/2020 JOHNNY WU
Plan Check Approved 8/6/2020 AMIR DANAI
Issued 8/10/2020 APPLICANT
Building Plans Picked Up 8/11/2020 APPLICANT
CofO in Progress 12/11/2020 DANIEL DREW
Permit Finaled 3/4/2021 MICHAEL SMITH
CofO Issued 3/4/2021 MICHAEL SMITH
Permit Finaled 3/4/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/22/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/24/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/24/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 7/24/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/27/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/11/2020 Partial Approval DAVID MATSON
Footing/Foundation/Slab 9/11/2020 Partial Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 9/15/2020 Approved BEAU COLLINS
Underground Mechanical 9/15/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 10/7/2020 Partial Approval DAVID MATSON
ELECTRICAL-Rough 10/7/2020 Partial Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 10/7/2020 Partial Approval DAVID MATSON
Green Building Rough 10/7/2020 Not Ready for Inspection DAVID MATSON
HVAC-Rough 10/7/2020 Approved DAVID MATSON
PLUMBING-Rough 10/7/2020 Approved DAVID MATSON
Underground Mechanical 10/7/2020 Partial Approval DAVID MATSON
Insulation 10/13/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 10/13/2020 Approved BEAU COLLINS
Drywall Nailing 10/16/2020 Approved BEAU COLLINS
ELECTRICAL-Final 12/8/2020 Not Ready for Inspection BEAU COLLINS
Final 12/8/2020 Corrections Issued BEAU COLLINS
Green Building Final 12/8/2020 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 12/8/2020 SGSOV Not Ready BEAU COLLINS
Smoke Detectors 12/8/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 12/11/2020 Approved DANIEL DREW
ELECTRICAL-Final 12/11/2020 Approved DANIEL DREW
Final 12/11/2020 OK to Issue CofO DANIEL DREW
Footing/Foundation/Slab 12/11/2020 Approved DANIEL DREW
Green Building Rough 12/11/2020 Approved DANIEL DREW
HVAC-Final 12/11/2020 Approved DANIEL DREW
PLUMBING-Final 12/11/2020 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 12/11/2020 SGSOV Approved DANIEL DREW