7761 N ARCOLA AVE 91352
Certificate Information: 7761 N ARCOLA AVE 91352
- Application / Permit
- 20016-10000-14221
- Plan Check / Job No.
- B20LA10579
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 25'-5"X20'-3 1/2" TO AND CONVERT THE EXISTING 20'-3'X20'-3 1/2" GARAGE INTO AN ACCESSORY DWELING UNIT. WORK WORK WFPP.
- Permit Issued
- Issued on 8/10/2020
- Issuing Office
- Current Status
- CofO Issued on 3/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2020 | JOHNNY WU |
| Corrections Issued | 6/18/2020 | JOHNNY WU |
| Plan Check Approved | 8/6/2020 | AMIR DANAI |
| Issued | 8/10/2020 | APPLICANT |
| Building Plans Picked Up | 8/11/2020 | APPLICANT |
| CofO in Progress | 12/11/2020 | DANIEL DREW |
| Permit Finaled | 3/4/2021 | MICHAEL SMITH |
| CofO Issued | 3/4/2021 | MICHAEL SMITH |
| Permit Finaled | 3/4/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 6/24/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 7/24/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/27/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/11/2020 | Partial Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/11/2020 | Partial Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 9/15/2020 | Approved | BEAU COLLINS |
| Underground Mechanical | 9/15/2020 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 10/7/2020 | Partial Approval | DAVID MATSON |
| ELECTRICAL-Rough | 10/7/2020 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Partial Approval | DAVID MATSON |
| Green Building Rough | 10/7/2020 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Rough | 10/7/2020 | Approved | DAVID MATSON |
| PLUMBING-Rough | 10/7/2020 | Approved | DAVID MATSON |
| Underground Mechanical | 10/7/2020 | Partial Approval | DAVID MATSON |
| Insulation | 10/13/2020 | Approved | BEAU COLLINS |
| Interior/Exterior Lathing | 10/13/2020 | Approved | BEAU COLLINS |
| Drywall Nailing | 10/16/2020 | Approved | BEAU COLLINS |
| ELECTRICAL-Final | 12/8/2020 | Not Ready for Inspection | BEAU COLLINS |
| Final | 12/8/2020 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 12/8/2020 | Approved | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 12/8/2020 | SGSOV Not Ready | BEAU COLLINS |
| Smoke Detectors | 12/8/2020 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 12/11/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 12/11/2020 | Approved | DANIEL DREW |
| Final | 12/11/2020 | OK to Issue CofO | DANIEL DREW |
| Footing/Foundation/Slab | 12/11/2020 | Approved | DANIEL DREW |
| Green Building Rough | 12/11/2020 | Approved | DANIEL DREW |
| HVAC-Final | 12/11/2020 | Approved | DANIEL DREW |
| PLUMBING-Final | 12/11/2020 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 12/11/2020 | SGSOV Approved | DANIEL DREW |