12866 W BONAPARTE AVE 90066

Certificate Information: 12866 W BONAPARTE AVE 90066

Application / Permit
20016-10000-14176
Plan Check / Job No.
B20LA10535
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 9/16/2020
Issuing Office
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 DANIEL YIP
Corrections Issued 7/16/2020 DANIEL YIP
Quality Review Completed 7/21/2020 HERNAN ARREOLA
Building Plans Picked Up 8/4/2020 APPLICANT
Plan Check Approved 9/15/2020 DANIEL YIP
Issued 9/16/2020 APPLICANT
CofO in Progress 8/23/2021 JOHNNY MIRANDA
Permit Finaled 9/21/2021 DANIEL ORRANTE
CofO Issued 9/21/2021 DANIEL ORRANTE
Permit Finaled 9/21/2021 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/31/2020 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 9/4/2020 NIKTA MOUSAVI
Green Code Cleared 9/15/2020 DANIEL YIP
Specific Plan Cleared 9/15/2020 FREDDY GARCIA

Contact Information

Architect Chung,, Myung Chul; Lic. No.: C17573 3034 LOS OLIVOS LANE      LA CRESCENTA, CA 91214
Contractor A Pixle Inc; Lic. No.: 974337-B 14532 FRIAR ST SUITE L      VAN NUYS, CA 91411

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/25/2020 Approved JOHNNY MIRANDA
Underground Mechanical 9/25/2020 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 9/30/2020 Corrections Issued JOHNNY MIRANDA
METHANE-Barrier 9/30/2020 Corrections Issued JOHNNY MIRANDA
METHANE-Subgrade 9/30/2020 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 10/2/2020 Partial Approval JOHNNY MIRANDA
METHANE-Barrier 10/2/2020 Approved JOHNNY MIRANDA
METHANE-Subgrade 10/2/2020 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 11/16/2020 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 11/16/2020 Corrections Issued JOHNNY MIRANDA
Green Building Rough 11/16/2020 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 11/16/2020 Approved JOHNNY MIRANDA
PLUMBING-Rough 11/16/2020 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 11/20/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 11/20/2020 Approved JUAN VALENZUELA
Green Building Rough 11/20/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 11/20/2020 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 11/25/2020 Partial Approval JOHNNY MIRANDA
Shower Pan 11/25/2020 Corrections Issued JOHNNY MIRANDA
Insulation 11/30/2020 Approved JOHNNY MIRANDA
Shower Pan 11/30/2020 Approved JOHNNY MIRANDA
Special/Order Compliance 12/8/2020 Approved JOHNNY MIRANDA
Special/Order Compliance 12/9/2020 Off-Hour Fees Due
Special/Order Compliance 1/21/2021 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 1/27/2021 Approved PIERRE VEGA
Drywall Nailing 2/2/2021 Approved DAVID HEINE
Gas Test 3/24/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Final 3/30/2021 Corrections Issued JOHNNY MIRANDA
Final 3/30/2021 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 3/30/2021 Approved JOHNNY MIRANDA
Green Building Final 3/30/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 3/30/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 3/30/2021 Approved JOHNNY MIRANDA
HVAC-Final 4/7/2021 Not Ready for Inspection PIERRE VEGA
Final 4/28/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/28/2021 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/28/2021 SGSOV Approved ENRIQUE MIRELES
Final 5/14/2021 Corrections Issued JOHNNY MIRANDA
Green Building Final 5/14/2021 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Final 8/9/2021 Not Ready for Inspection BRENDAN LOONEY
Final 8/9/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Final 8/9/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Final 8/9/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 8/9/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 8/20/2021 Approved JOHNNY MIRANDA
Final 8/20/2021 OK to Issue CofO JOHNNY MIRANDA
Green Building Final 8/20/2021 Approved JOHNNY MIRANDA
HVAC-Final 8/20/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 8/20/2021 Approved JOHNNY MIRANDA