15739 W VENTURA BLVD 91436

Certificate Information: 15739 W VENTURA BLVD 91436

Application / Permit
20016-10000-14171
Plan Check / Job No.
B20LA10532
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
EXTERIOR & INTERIOR T.I :RENOVATION OF (E) CHAPEL & BRIDE'S ROOM - NEW DOORS, NEW FINISHES & NEW EXTERIOR STUCCO AT CHAPEL & ACCESSIBLE UPGRADE OF (E) RESTROOMS
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
Permit Finaled on 10/1/2021

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 GARO TELMI
Corrections Issued 7/15/2020 GARO TELMI
Quality Review Completed 7/20/2020 CHAD DOI
Disabled Access Plans Picked Up 8/19/2020 APPLICANT
Applicant returned to address corrections 1/7/2021 GARO TELMI
Plan Check Approved 2/5/2021 GARO TELMI
Issued 3/25/2021 APPLICANT
Building Plans Picked Up 4/1/2021 APPLICANT
Permit Finaled 10/1/2021 ANDREW DORSO

Permit Application Clearance Information

Automotive Use Cleared 8/5/2020 SARAHI ORTEGA
CPC Cleared 8/5/2020 SARAHI ORTEGA
Specific Plan Cleared 8/5/2020 SARAHI ORTEGA
Fire Marshall Fire Life Safety Cleared 12/22/2020 VIDAL GARCIA
DAS Clearance Cleared 1/7/2021 GARO TELMI

Contact Information

Architect Abramson,, Trevor David; Lic. No.: C17597 8924 LINDBLADE STREET      CULVER CITY, CA 90232
Contractor Driver S P G Llc; Lic. No.: 960119-B 468 NORTH ROSEMEAD BLVD      PASADENA, CA 91107
Engineer Cocke,, David Winbern; Lic. No.: S3005 19210 S VERMONT AVENUE BLDNG B SUITE 210      GARDENA, CA 90248

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/5/2021 Partial Inspection CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 5/27/2021 Conditional Approval ROBERT DAVIS
Light Gage Steel Frame 7/6/2021 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 7/22/2021 Conditional Approval DANIEL VARNUM
Insulation 7/27/2021 Approved CAMERON CHABAN
Structural Steel Frame 7/27/2021 Approved CAMERON CHABAN
Drywall Nailing 8/4/2021 Approved CAMERON CHABAN
Interior/Exterior Lathing 8/9/2021 Approved CAMERON CHABAN
Final 9/3/2021 Not Ready for Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 9/3/2021 SGSOV Gas Company CAMERON CHABAN
Smoke Detectors 9/3/2021 Approved CAMERON CHABAN
Final 9/10/2021 Partial Inspection CAMERON CHABAN
Final 9/20/2021 Not Ready for Inspection JOE VELASQUEZ
Final 9/22/2021 Not Ready for Inspection JOE VELASQUEZ
Final 10/1/2021 Permit Finaled ANDREW DORSO