5952 N FALLBROOK AVE 91367
Certificate Information: 5952 N FALLBROOK AVE 91367
- Application / Permit
- 20016-10000-13983
- Plan Check / Job No.
- B20LA10399
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- CHANGE OF USE FROM EXISTING DRUG STORE TO NEW MARKET PLACE AND 8 NEW 200LB ROOFTOP UNIT
- Permit Issued
- Issued on 4/7/2021
- Issuing Office
- Current Status
- CofO Issued on 3/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2020 | SAM CHANG |
| Corrections Issued | 6/16/2020 | SAM CHANG |
| Applicant returned to address corrections | 7/13/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 9/28/2020 | STARR CHEN |
| Plan Check Approved | 4/7/2021 | ADAM HEGAZI |
| Issued | 4/7/2021 | APPLICANT |
| Building Plans Picked Up | 4/8/2021 | APPLICANT |
| CofO in Progress | 3/30/2023 | BRIAN KELLY |
| CofO Issued | 3/31/2023 | JEFFREY DURAN |
| Permit Finaled | 3/31/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Food establishment approval | Cleared | 6/16/2020 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 10/19/2020 | KENNETH BROWNE |
| "Q" conditions | Cleared | 10/22/2020 | LOUIS ORTEGA |
| CPC | Cleared | 10/22/2020 | LOUIS ORTEGA |
| ZA Case | Cleared | 10/22/2020 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/2/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | T I Industry Corporation; Lic. No.: 853358-B | 8128 ORSON AVENUE VAN NUYS, CA 91406 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 6/9/2021 | Partial Inspection | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 6/9/2021 | SGSOV Not Ready | CAMERON CHABAN |
| Smoke Detectors | 6/9/2021 | Approved | CAMERON CHABAN |
| Final | 6/16/2021 | Partial Inspection | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 6/16/2021 | SGSOV Approved | CAMERON CHABAN |
| Final | 1/12/2023 | Not Ready for Inspection | BRIAN KELLY |
| Pre-Inspection | 1/12/2023 | Approved | BRIAN KELLY |
| Final | 3/6/2023 | OK to Issue CofO | BRIAN KELLY |