5670 S MARGARET AVE 90230
Certificate Information: 5670 S MARGARET AVE 90230
- Application / Permit
- 20016-10000-13727
- Plan Check / Job No.
- B20LA10219
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT AND REMOVE AND REPLACE SHINGLES. ALL WORK PER TYPE V SHEET.
- Permit Issued
- Issued on 10/7/2020
- Issuing Office
- Current Status
- CofO Issued on 1/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/11/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/3/2020 | RACHEL BEYENE |
| Building Plans Picked Up | 9/10/2020 | APPLICANT |
| Issued | 10/7/2020 | APPLICANT |
| CofO in Progress | 1/6/2022 | DAVID FEILER |
| Permit Finaled | 1/8/2022 | DANIEL ORRANTE |
| CofO Issued | 1/8/2022 | DANIEL ORRANTE |
| Permit Finaled | 1/8/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2020 | DINAH GARIN |
| Sewer availability | Cleared | 6/25/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2020 | DINAH GARIN |
| Permit | Cleared | 6/30/2020 | DINAH GARIN |
| Trees in Parkway | Cleared | 7/21/2020 | JOHN KIM |
| Construction near power lines | Cleared | 8/23/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Expo Home Design & Remodeling Inc; Lic. No.: 911716-B | 12725 VENTURA BLVD #D STUDIO CITY, CA 91604 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/13/2020 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 10/19/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/19/2020 | Partial Approval | JOHNNY MIRANDA |
| MERV13>=Final | 10/19/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 10/19/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Final | 10/19/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 10/19/2020 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 10/19/2020 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 10/19/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/4/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 11/4/2020 | Corrections Issued | JOHNNY MIRANDA |
| MERV13>=Rough | 11/4/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 11/4/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 11/4/2020 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/16/2020 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/16/2020 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 11/16/2020 | Approved | JOHNNY MIRANDA |
| Insulation | 12/2/2020 | Corrections Issued | JOHNNY MIRANDA |
| Insulation | 12/7/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 12/10/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 12/11/2020 | Conditional Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/11/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/28/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/28/2020 | Partial Approval | JOHNNY MIRANDA |
| MERV13>=Rough | 12/28/2020 | Approved | JOHNNY MIRANDA |
| Final | 3/5/2021 | Corrections Issued | DAVID HEINE |
| MERV13>=Final | 3/5/2021 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 3/5/2021 | SGSOV Approved | DAVID HEINE |
| Smoke Detectors | 3/5/2021 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 4/14/2021 | Approved | JOHNNY MIRANDA |
| Final | 7/22/2021 | Corrections Issued | JOHNNY MIRANDA |
| Final | 9/20/2021 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 9/20/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 9/20/2021 | Approved | JOHNNY MIRANDA |
| Final | 11/3/2021 | Corrections Issued | DAVID FEILER |
| Final | 12/21/2021 | OK to Issue CofO | DAVID FEILER |
| Service/Power Release | 1/7/2022 | Approved | DAVID FEILER |