12088 W MOUND VIEW PL 91604

Certificate Information: 12088 W MOUND VIEW PL 91604

Application / Permit
20016-10000-13613
Plan Check / Job No.
B20LA10123
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) accessory living quarter and recreation room on 2nd floor to ADU per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 8/31/2020
Issuing Office
Current Status
CofO Issued on 5/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 CRISTINA SALAZAR
Corrections Issued 6/11/2020 CRISTINA SALAZAR
Plan Check Approved 8/19/2020 SAMUEL GONZALEZ
Building Plans Picked Up 8/19/2020 APPLICANT
Issued 8/31/2020 APPLICANT
CofO in Progress 4/19/2022 ARAM AVEDISIAN
CofO Issued 5/11/2022 MICHAEL SMITH
Permit Finaled 5/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/6/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/6/2020 GABRIEL ROBLES
Sewer availability Cleared 8/6/2020 GABRIEL ROBLES

Contact Information

Architect Phakos,, Cynthia; Lic. No.: C23352 9010 RANGELY AVE      WEST HOLLYWOOD, CA 90048
Contractor Raub Doug Design & Development Inc; Lic. No.: 723625-B 14066 ROBLAR ROAD      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/8/2020 Approved ARAM AVEDISIAN
HVAC-Rough 9/11/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 9/11/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/14/2021 Partial Approval THOMAS FINNILA
Shower Pan 1/14/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 1/10/2022 Corrections Issued JACK KARGODORIAN
HVAC-Final 1/10/2022 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Final 1/10/2022 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 1/18/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 1/18/2022 Approved ARAM AVEDISIAN
HVAC-Final 1/18/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Final 1/18/2022 Approved ARAM AVEDISIAN
Final 4/18/2022 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/18/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 4/18/2022 Approved ARAM AVEDISIAN
Final 4/19/2022 OK to Issue CofO ARAM AVEDISIAN