4776 W DON MIGUEL DR 90008
Certificate Information: 4776 W DON MIGUEL DR 90008
- Application / Permit
- 20016-10000-13538
- Plan Check / Job No.
- B20LA10050
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Using 2 SCCS
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofC Issued on 12/19/2023
Permit Application Status History
| Submitted | 6/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2020 | VARAND SARKISIAN |
| Corrections Issued | 7/27/2020 | VARAND SARKISIAN |
| Quality Review Completed | 7/28/2020 | SAI KHUM |
| Applicant returned to address corrections | 9/2/2020 | VARAND SARKISIAN |
| Applicant returned to address corrections | 10/15/2020 | VARAND SARKISIAN |
| Applicant returned to address corrections | 11/2/2020 | VARAND SARKISIAN |
| Plan Check Approved | 12/4/2020 | VARAND SARKISIAN |
| Issued | 3/25/2021 | APPLICANT |
| OK for CofC | 12/1/2023 | JACOB MYERS |
| CofC Issued | 12/19/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 11/5/2020 | ARMEN SARKISIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2020 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 3/25/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/12/2021 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 4/26/2021 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 4/26/2021 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 4/29/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 5/3/2021 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 5/3/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 5/3/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/19/2021 | Approved | DARRYL ARNOLD |
| Final | 11/3/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/3/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 12/1/2023 | OK for CofC | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | JACOB MYERS |
| Smoke Detectors | 12/1/2023 | Approved | JACOB MYERS |