11509 S MENLO AVE 90044
Certificate Information: 11509 S MENLO AVE 90044
- Application / Permit
- 20016-10000-13514
- Plan Check / Job No.
- B20LA10027
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ADU.
- Permit Issued
- Issued on 7/27/2020
- Issuing Office
- Current Status
- CofO Issued on 2/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2020 | ADAM HEGAZI |
| Corrections Issued | 6/10/2020 | ADAM HEGAZI |
| Plan Check Approved | 7/14/2020 | RICARDO RAMIREZ |
| Issued | 7/27/2020 | APPLICANT |
| Building Plans Picked Up | 7/29/2020 | APPLICANT |
| CofO in Progress | 1/28/2021 | EUGENE CASSIDY |
| Permit Finaled | 2/11/2021 | DEROLD HAUFF |
| CofO Issued | 2/11/2021 | DEROLD HAUFF |
| Permit Finaled | 2/11/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/23/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 6/23/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | A A A All Star Construction Inc; Lic. No.: 1018926-A | 12500 RIVERSIDE DRIVE 201A VALLEY VILLAGE, CA 91607 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/17/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2020 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/20/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/10/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/10/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 9/10/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 9/10/2020 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 9/10/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/10/2020 | Approved | EUGENE CASSIDY |
| Insulation | 9/18/2020 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 9/18/2020 | Corrections Issued | DAVID FEILER |
| Drywall Nailing | 9/29/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/29/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2020 | Approved | EUGENE CASSIDY |
| Final | 12/31/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 12/31/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Final | 12/31/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/31/2020 | SGSOV Not Required | EUGENE CASSIDY |
| Smoke Detectors | 12/31/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 1/14/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 1/14/2021 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 1/14/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/28/2021 | Approved | EUGENE CASSIDY |
| Final | 1/28/2021 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 1/28/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/28/2021 | Approved | EUGENE CASSIDY |