20945 S DENKER AVE 90501
Certificate Information: 20945 S DENKER AVE 90501
- Application / Permit
- 20016-10000-13465
- Plan Check / Job No.
- B20LA09991
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF 456 SQFT (E) DETACHED GARAGE INTO AN ADU.
- Permit Issued
- Issued on 10/29/2020
- Issuing Office
- Current Status
- CofO Issued on 2/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2020 | CRISTINA SALAZAR |
| Corrections Issued | 6/15/2020 | CRISTINA SALAZAR |
| Building Plans Picked Up | 6/17/2020 | APPLICANT |
| Plan Check Approved | 8/4/2020 | CHUNG-WEN CHUANG |
| Issued | 10/29/2020 | APPLICANT |
| CofO in Progress | 2/11/2021 | JOHN KLARIN |
| Permit Finaled | 2/27/2021 | DEROLD HAUFF |
| CofO Issued | 2/27/2021 | DEROLD HAUFF |
| Permit Finaled | 2/27/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2020 | JEANIE LAM |
| Sewer availability | Cleared | 7/9/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2020 | JEANIE LAM |
Contact Information
| Architect | Khaleeli,, Bizhan; Lic. No.: C29971 | 27823 SOUTH MONTEREINA DRIVE PALOS VERDES ESTATES, CA 90275 |
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/3/2020 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 12/10/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/28/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 12/28/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 12/28/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 12/28/2020 | Approved | JOHN KLARIN |
| Underground Mechanical | 12/28/2020 | Approved | JOHN KLARIN |
| Wood Frame | 12/28/2020 | Approved | JOHN KLARIN |
| Insulation | 12/31/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 12/31/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 1/8/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 2/1/2021 | Approved | JOHN KLARIN |
| Final | 2/1/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 2/1/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 2/1/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2021 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 2/1/2021 | Approved | JOHN KLARIN |
| Final | 2/10/2021 | OK to Issue CofO | JOHN KLARIN |